290 likes | 630 Views
The Critical Path – Precedence diagram method. Luise Lorenz Christina Mohr. Critical Path Method (CPM). Project planning technique Important tool for project management For any project with interdependent activities. CPM helps you figure out:.
E N D
The Critical Path – Precedence diagram method Luise Lorenz Christina Mohr
Critical Path Method (CPM) • Project planning technique • Important tool for project management • For any project with interdependent activities
CPM helps you figure out: • how long a complex project will take to complete • which activities are critical • those needed to be done in time in order to follow the schedule
The model of CPM • A list of all activities required to complete a project • The duration of each activity has to be known • Analyze the dependencies between the activities
The model of CPM • CPM calculates the longest path of planned activities to the end • Earliest and latest date that each activity can start and finish • Avoiding extension of the project • Determining the ‚critical‘ activities • Activities which have ‚total float‘ (delayed without making the project longer)
Critical path • Series of project network activities which lead to the longest overall duration • Shortest time to complete a project • Delay of critical activity has an impact on the completion date • Shorten the planned critical path by ‚fast tracking‘ (more activities parallel) or ‚crashing the critical path‘ (shortening activities by adding resources)
Precendence diagram method (PDM) • Network diagram uses boxes to represent activities • Connection with arrows to show the dependencies • Early / late start date • Early / late finish date • Duration
Advantages of PDM • Finding the critical path • Defining the amount of time required • Usage to crash projects • To reduce resources • Defining dependencies • Identifying lead and lag times
Design I LS (Latest Start) LF (Latest Finish) ES (Earliest Start) EF (Earliest Finish) Operation Description Duration Ref. No. Float if the float equals zero it‘s considered critical
Design II ES EF Duration Operation Description Float LS LF if the float equals zero it‘s considered critical
Example B C 1 2 4 2 1 1 A F D E
Example B C 1 2 4 2 1 1 0 1 A F D E
Example 1 B C 1 2 1 2 1 4 0 1 A F 1 D E
Example 1 3 B C 4 2 1 2 1 1 0 1 A F 1 2 D E
Example 1 3 3 B C 2 1 1 2 4 1 0 1 A F 1 2 2 D E
Example 1 3 3 7 B C 1 4 2 1 1 2 0 1 A F 1 2 2 3 D E
Example 1 3 3 7 B C 1 2 1 2 1 4 0 1 7 9 A F 1 2 2 3 D E
Example 1 3 3 7 B C 1 2 4 2 1 1 0 1 7 9 A F 7 9 1 2 2 3 D E
Example 1 3 3 7 B C 1 2 4 2 1 1 0 1 7 9 A F 7 0 9 1 2 2 3 D E
Example 1 3 3 7 B C 7 1 2 4 2 1 1 0 1 7 9 A F 7 0 9 1 2 2 3 D E 7
Example 1 3 3 7 B C 3 0 7 1 1 4 2 1 2 0 1 7 9 A F 7 0 9 1 2 2 3 D E 6 4 7
Example 1 3 3 7 B C 1 0 3 3 0 7 4 1 1 2 2 1 0 1 7 9 A F 7 0 9 1 2 2 3 D E 5 4 6 6 4 7
Example 1 3 3 7 B C 1 0 3 3 0 7 4 2 1 1 2 1 0 1 7 9 A F 0 0 1 7 0 9 1 2 2 3 D E 5 4 6 6 4 7
Example 1 3 3 7 B C 1 0 3 3 0 7 4 2 1 1 2 1 0 1 7 9 A F 0 0 1 7 0 9 1 2 2 3 D E 5 4 6 6 4 7