260 likes | 361 Views
Dubna GDE Workshop ОИЯИ , Дубна, 0 4-06 .06.2008. Marc Ross, Akira Yamamoto, Nick Walker GDE Project Managers. Goals for 2008: Cost and Risk reduction SCRF CERN engagement R&D Plan Consolidation of RDR cost estimate To be reported LCWS 08 Chicago. Post RDR – ILC. One year later:
E N D
Dubna GDE WorkshopОИЯИ, Дубна, 04-06.06.2008 Marc Ross, Akira Yamamoto, Nick Walker GDE Project Managers • Goals for 2008: • Cost and Risk reduction • SCRF • CERN engagement • R&D Plan • Consolidation of RDR cost estimate • To be reported LCWS 08 Chicago M. Ross for PM - ILCGlobal Design Effort
Post RDR – ILC • One year later: • Focus on R&D • to mitigate technical risk • (some of which assumed for RDR) • to enable cost reduction • Managing the RDR • held kick off meetings • working on consolidating cost information • Strengthening links with partners • multi-lateral GDE • ca. 400 members M. Ross for PM Global Design Effort
Superconducting RF R&D Three components to SCRF R&D: • Gradient (S0) • 35 MV/m baseline cavity gradient • should be able to build two x 11 km cold linacs with operational gradient 10% below this realistically; practically • Demonstrations underway! • Plug Compatibility (includes S1) • Purpose: • Encourage innovation in R&D phase • Motivate practical ‘Project Implementation’ • System Tests (S2) • show that the whole complex functions M. Ross for PM Global Design Effort
ILC SCRF R&D - 2008 Where are we? What has been done in 2008? Gradient (S0) Cavity • 10.2007 : • results from 15 cavities (DESY - Zanon) • some cavities tested many times; • field emission reduced using ethanol rinse • Average 31.5 MV/m • 06.2008 : • new batch of cavities (Accel) – 5 tested • industrial bulk electro-polish • first DESY - Accel results with ethanol rinse to suppress field emission • Accel Average: 36.2 MV/m • 850 cavities to be ordered this year for XFEL / EU FP7 • additional optical inspection systems in fabrication M. Ross for PM Global Design Effort
ILC SCRF R&D - 2008 • Plug Compatibility (included in S1) Cryomodule • Progress toward consensus: due 2008 • This is a real step toward ‘industrialization’ for a global ILC • System Tests (S2) RF Unit • Partly started with ‘FLASH / TTF, 9 mA test’ • Full beam loading, high gradient (~ 30 MV/m avg) March 2009 M. Ross for PM Global Design Effort
Accelerator Systems R &D: Beam Tests • Damping Ring Beam dynamics – electron cloud • CesrTA program moving forward • Thanks to strong KEK / NSF-DOE support • beam tests now underway • First results LCWS 08 Chicago • Beam Delivery – Stabilization and Precision • ATF2 International Collaboration • First beam October 2008 M. Ross for PM Global Design Effort
Chambers with Thin RFAs • Loss of US collaborators impacted development heavily • Cornell has picked up detailed design • Now ready for final design review • Construction now starting at LBNL as part of CU-KEK-LBNL-SLAC collaboration RFA Wiggler VC Delivered CesrTA Superconducting wiggler instrumented vacuum chamber
ATF2 - 2008 M. Ross for PM Global Design Effort
CFS Value Engineering • RDR is our baseline • strong, valid cost and design basis • the ‘uniform’ (teamwork-based) site development approach – • working closely together / • consolidating resources • Specific FOCUS GROUP goals for this workshop: • ‘Quantify cost impact for near-surface scenarios’ • requirement matrix • Develop ‘parametric models for infrastructure requirements’ • M. Ross for PM Global Design Effort
Cost cutting by increasing the temperature difference Fixed costs: chillers, pressed air, water treatment, auxiliary pipes, etc recooler: constant temperature difference for the heat flow at the cold side (e.g. the air temperature) insulation: always the same heat flow The outlet temperature should be less than 70°C: Otherwise the water will be to hot for some equipments
CFS Value Engineering (2) The purpose of this workshop • (hence inter-group ‘focus groups’) • The Dubna shallow site: • subsurface ‘communication building’ cost 1/10 bored tunnel • RDR WBS input from GSPI (ГСПИ) to be provided • Next step: • Joint Development of Dubna site: • GDE (EU), JINR, GSPI • How to take best advantage of special features… M. Ross for PM Global Design Effort
The Minimum Machine Study Are we here? cost cost Aim for here 500 GeV21034 cm-2s-1 Margin, risk reduction, redundancy, …(indirect performance) Physics “figure of Merit”(direct performance) Minimum cost machine Understand the performance derivatives Global Design Effort Global Design Effort
Towards a ‘Minimum Machine’ Configuration Working Groups: Siting: Examine possible sites and evaluate possible design differences that accommodate features. Includes staging, design modifications and upgrade issues. Accelerator Systems: particular focus on the central injection complex, BDS and RTML. Beginning of the process of: Re-thinking the layout of the machine for a lower cost Look for new and innovative ideas – particularly staging options Defining the ‘minimum machine’ layout Global Design Effort Global Design Effort
Output of Workshop sets the typical scale of possible reduction • Significant potential identified: • 4-5 km tunnel and beamline • ~100 MILCU for CFS • ~100 MILCU for acceleratorcomponents • All of the items discuss have associated impact on performance which will need to be quantified • Action items for LCWS • CMG and relevant TAG leaders Global Design Effort Global Design Effort
Milestone – Dubna GDE meeting: • Release of the ILC Technical Design Phase R & D Plan • today • The plan includes an outline of our • strategy • work plan • schedule • deliverables • resources • constituency • very useful for management, reviews, funding agencies, … M. Ross for PM Global Design Effort
R&D Plan Release 2 Look! NO DRAFT! Released today Next review and release:December 08 Global Design Effort Global Design Effort
PM TD Phase 1 & 2 Schedule • A tentative top-level management plan for TD Phase 1 & 2 now exists • Published in R&D Plan • More detailed schedule being updated • MS Project • Part of release 2 • Encapsulates the PMs strategy and vision for the next four years • Critical R&D • Cost reduction / machine design • Project Implementation Plan Global Design Effort
THE RDR LIVES ON ! Understanding the scope of the TDR (design/cost) work M. Ross for PM Global Design Effort
CLIC-ILC Cost & Schedule Group Summary, future tasks • Two specific topics for collaboration: progress to be reported on at the CLIC workshop in October… • Defining common templates that will be gathered and/or used to catalog cost estimates from the technical groups • Timely, since both groups are in the process of developing such templates. • Could allow use of common analysis and reporting tools • Strongly linked with cost management processes and tools • Defining cost management processes and associated tools • Requires consideration of how the cost estimate data will be used: report generation, analyses, trade studies, etc • The CLIC group will be invited to participate in discussions on requirements for consultancy • Has a short timeframe for the ILC group since we are in the process of engaging a consultancy to support developing of cost management tools. • General comment: both groups are interested in learning from each other. Additional topics that came up during discussions include: • Structuring and organizing cost estimate information and bases of estimates • Handling uncertainty and risk in the cost estimates John Carwardine: [date] Global Design Effort Global Design Effort 23
GDE Meetings: you requested: • fewer meetings: 3 down to 2. • One ‘collaboration-wide’ LCWS 08 Chicago • broad attendance and comprehensive program, please! • structure based on our Technical Area Groups • One thematic (this is the first) • Proposed for early 2009: • AAP Review – 3 days, plenary 2 days • advance planning • Conveners, focus / working groups M. Ross for PM Global Design Effort
Homework for LCWS 08 Chicago: based on Dubna priorities: • CFS / Accelerator Design updates • Cost reduction • CFS change requests • complete Value Engineering cycle started here • Collaboration work and reports (e.g. CLIC – ILC) • R & D Plan updates • trade offs developed here • (the basis of value engineering is cost/performance trade off) M. Ross for PM Global Design Effort
To our JINR Hosts: • Позвольте выразить Вам от всего сердца бесконечную благодарность за проведение Совещания, за отличную организацию, гостеприимство и заботу! • Спасибо! • Thank you! • Excellent hospitality! Excellent organization! • Beautiful surroundings, excellent location, excellent logistics, etc! M. Ross for PM Global Design Effort