DEX Publication Project OASIS PLCS TC Face to Face meeting 10 March 2008 Trine Hansen
Overall status • The main deliverables are completed • 2 DEXs are ready for TC ballot • 110 templates are ready for TC ballot • Harmonization between the two Task DEXs are completed • Some deliverables remains • Project Manager requests a final Core Team workshop for summing up lessons learned and recommend way forward for TOG PLCS Inc. (c) 2002
Project Summary PLCS Inc. (c) 2002
Project Initiation & Scope Steering Group established. Proj. Plan v1 2 DEXs,110 Templates ready for TC ballot TC mtg.Huntsville Postpone Capabilities Proj Plan v2 1 Oct 07 10 March 08 31 Oct 06 25 April 07 9 Feb 07 • Scope • 2 DEXs • Templates • Reference data • Scope • 2 DEXs • Templates • Capabilities • Reference data • Scope • 4 DEXs • Templates • Capabilities • Reference data PLCS Inc. (c) 2002
Summary of meetings • Steering Group telecons: 17 • Core team face-to-face meetings: 5 • Harmonization workshops (Task DEX): 8 • Core team telecons: >>20 • Report to OASIS PLCS TC: 8 (Telecons and face to face meetings) • Other meetings: 4 • For more details: See Attachments PLCS Inc. (c) 2002
Status per Activity • Reported per Delivery listed in • the Project Plan PLCS Inc. (c) 2002
Activity #1 - Management • Detailed project plan: Done • Status reports: Done • Minutes: Done PLCS Inc. (c) 2002
Activity #2 - Core Team Activities • OASIS requirements for publication of DEXs • Status: Preliminary but no final comments received • Review checklists: Done • DEX related concepts to be documented in the DEXLib ‘Help’ section. Includes relationships between the concepts. Status: Done • Procedures for review and harmonization activities • Status: Proposal documented. Core Team resolution remains PLCS Inc. (c) 2002
Activity #3 TOG Support Management • Requirements for standardization of DEXs and related concepts in OASIS: Done • Requirements for tool support of future TOG management activities: Not completed • Requirements for procedures for handling request for external support: Not completed PLCS Inc. (c) 2002
Activity #4 Check lists and Processes • Review check lists for • Templates: Done • Reference data: Done • Capabilities: Not scope • DEXs: Done • DEXLib Help section: Done • Documentation of processes to support the development and review activities: Not completed PLCS Inc. (c) 2002
Activity #5 DEXLib infrastructure • Specify software: Done • Develop software test plan: Done • Implement software: Done • Test plan for new DEXLib functionalities: Done • Acceptance test according to Test plan including report from the test: Done • Functionality to generate DEX longform from templates: Done • P28 generation according to the P28 IS version: Done • Explicit representation of business DEXs: Done • Explicit representation of business objects: Not scope • DEX release environment in DEXLib: Done PLCS Inc. (c) 2002
Activity #5 DEXLib infrastructure • Usage reporting tool: Done • Remove bugs according to prioritizing: Done • Functionality to identify revisions of templates, modules etc. witch a DEX is made of: Done • Version controlled OWL files (reference data): Done • Specification for how to convert the HTML version of DEXLib into other document formats: Done • Normalized form of OWL: Not scope • Hyperlink functionalities in Graphical Express: Not scope • Hyperlink functionalities in Graphical Instance: Not scope • Functionality to store and index the test data : Not scope PLCS Inc. (c) 2002
Activity #6 - DEXlib Help section • Documentation in DEXlib Help section supporting deliverables from other activities in this project. Includes ‘business expert’ level of the documentation: Done • Requirements for links between PLCS activity model and central concepts: Not completed • Review comments and issues: Done PLCS Inc. (c) 2002
Activity #7 –Develop, review and update “core” templates • Templates documented in DEXLib according to agreements (documented in review checklists): Done • Findings from review activities documented in DEXLib: Done • Updated templates according to review comments and harmonization activities: Done PLCS Inc. (c) 2002
Activity #8 –Develop, review and update “core” capabilities • Status: Not in scope PLCS Inc. (c) 2002
Activity #9 – Develop, review and update DEX specific templates • Templates documented in DEXLib according to agreements (documented in review checklists): Done • Findings from review activities documented in DEXLib: Done • Updated templates according to review comments and harmonization activities: Done PLCS Inc. (c) 2002
Activity #10 – Develop, review and update DEX specific capabilities • Status: Not in scope PLCS Inc. (c) 2002
Activity #11 - Develop and harmonize DEXs • DEXs documented in DEXLib according to agreements (reflected in review checklists): Done PLCS Inc. (c) 2002
Activity #12 - Review DEXs • Documentation of findings from the review activity: Done • Updated DEX documentation in DEXLib according to agreements: Done PLCS Inc. (c) 2002
Activity #13 - Preparations for establishing Implementers Forum • Plan for Implementers Forum : Not done (on the agenda for this meeting) PLCS Inc. (c) 2002
Activity #14 – Final report • Status: Started, not completed PLCS Inc. (c) 2002
Remaining deliverables PLCS Inc. (c) 2002
Remaining deliverables • TOG support management • Requirements for tool support of future TOG management activities • Requirements for procedures for handling request for external support • Procedures for support of development and review activities • Requirements for links between PLCS activity model and central concepts • Plan for Implementers Forum (TC meeting 10-11 March 08) • Final report • Lessons learned, recommended way forward PLCS Inc. (c) 2002
Request from Project Manager • Final Core Team workshop in UK (17-18, 21-22 April 08) • TOG leader participation • Deliverables • Lessons learned • Recommendations for further TOG activities • Maintenance of Information pages • Identification/acceptance of development of new DEXs, templates etc. • Harmonization activities (Reference data, use of PLCS schema) • How to maintain Capabilities/user guidance • And more…… • Proposed plan for further activities • Addressing ballot comments • Results from workshop input to Final report PLCS Inc. (c) 2002
Project Budget • The Steering Group: • NDLO: Tor Arne Irgens (Chairman) • BAE Systems: Howard Mason (Deputy Chair) • FMV: Mats Elgh • UK MOD: Martin Gibson • DOD: Jim Colson • DNV: Nils Sandsmark • EPMT: Jorulv Ragnes • Eurostep: Torbjørn Holm PLCS Inc. (c) 2002
Summary of Deliverables PLCS Inc. (c) 2002
Deliverables (1 of 3) • Management • Project Plan (draft, first and second revision) • Status reports (5 in total) • Various Minutes and presentations • 2 DEXs ready for ballot • Task Set DEX • Aviation Maintenance DEX • 110 Templates • Task Set DEX: 81 • Aviation Maintenance DEX: 62 • Large degree of common templates PLCS Inc. (c) 2002
Deliverables (2 of 3) • Information pages (DEXlib Help section) • Checklists • Template review • DEX review • Reference data (annotation properties) • Information/Help pages review • Acceptance test plan for DEXlib infrastructure • 110 template review checklists filled out • Addressed review comments PLCS Inc. (c) 2002
Deliverables (3 of 3) • DEXlib infrastructure • Tool supporting DEX, Business DEX, capability, template and reference data development • DEX Long form generation • Part 28 generation • Release environment • Usage reporting tool • Configuration change management (including reference data) PLCS Inc. (c) 2002
Final Delivery PLCS Inc. (c) 2002
Final delivery • The main delivery consists of DEXlib (2 DEXs, 110 templates, ref data, DEXlib infrastructure) and Final report • The following will be handed over to the Steering Group at the end of the project • Final report • Project plan • Status reports • Various Minutes PLCS Inc. (c) 2002
Attachments PLCS Inc. (c) 2002
Summary of meetings (1 of 3) • Steering group telecons: 17 • April 07: 3 • May 07: 3 • August 07: 3 • September + October 07: 4 • February 08: 4 • Core team face-to-face meetings: 5 • 13-15 February 97 (kick-off) • 13 April 07 (Reference data) • 25-27 April 07 (Reference data) • 18 June 07 (Ref. data process. London) • 3 July 07 (London) PLCS Inc. (c) 2002
Wrap-up: Summary of meetings (2 of 3) • Harmonization workshops (Task DEX): 8 • 15 May 07 (Oslo) • 4-5 June 07 (Stockholm) • 4-5 July 07 (Oslo) • 13-14 August 07 (Väksjö) • 2-3 October 07 (Oslo) • 21-23 November 07 (Stockholm) • 18-19 December 07 (Oslo) • 11-12 February 07 (Oslo) • Core team telecons: 20 ++ • April 07: 4 • May 07: 3 • August 07: 5+ • September and October 07: 3 • February 08: 5+ PLCS Inc. (c) 2002
Wrap-up: Summary of meetings (3 of 3) • Report to OASIS PLCS TC: 8 • April 07: 2 • May 07: 1 • August 07: 1 • September and October 07: 2 (including face-to-face) • February 08: 2 • Other meetings: 4 • 21 June 07: TOG resolution telecon • 23 July 07: Telecon with OASIS – publication requirements • 26 November 07: DEXlib acceptance test • Various Core Team telecons for addressing review comments PLCS Inc. (c) 2002
The end PLCS Inc. (c) 2002