ASKAP 2013 Year in review Ant Schinckel | ASKAP Theme Leader 17 December 2012 Astronomy and space science
HSE • Zero lost time injury (LTIs) • Record maintained over life of project(six years!) • Few incidents or near-misses • 4WD driver training • Bush fire fighting • Snake handling • Remote area first aid
Site and site support • MRO infrastructure complete • (except the power station) • BETA installation complete • MSF opened 4 July • Fibre link upgraded to 40+ Gb/s
ASKAP – Digital Systems • Processor and Data acquisition cards • Next V7 evolution • Successes with • BETA Correlator • BETA Beamformer • Firmware development • 2 sites ASKAP: CDSCC September 2013
Computing • Pawsey Centre opened 7 August, Operations launched 15 Nov. • Early adopter access and integration tests • Supporting BETA • “Epic” & “Magnus” • Supporting MWA • archival storage • CSIRO ASKAP Science Data Archive (CASDA)
Early science • ASKAP Early Science Workshop • 70 attendees, 14 institutes, 5 countries • ASKAP Early Science Program (draft) released 26 September • Early Science Simulations • Preliminary ASKAP-12 layout
Project management • Passed audit against CSIRO Major Project Standard (May) • Compliant with 30 of 36 standards • No non-compliances • Passed Chief Executive Audit (August) • Risk Assessment & Audit audit – in progress Funding • SIEF – $6m for PAFs + $6m CSIRO capex • AAL/NCIRS – $6m for ATNF ops +$6m CSIRO capex Presentation title | Presenter name