Study of the case “La Riereta ” Urban Drainage basin

Study of the case “La Riereta ” Urban Drainage basin. Team 1 Maximiliano Cavenaghi Kattia Arnez Ferrel Diego Alves Melo Jorge Marega Ramiro Marcus. Methodology. Delimitation and discretization of study area. Determination of hydraulic parameters. Determination of effective rainfall.

aleron
Download Presentation

Study of the case “La Riereta ” Urban Drainage basin

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Study of the case “La Riereta”Urban Drainage basin Team 1 MaximilianoCavenaghi KattiaArnezFerrel Diego Alves Melo Jorge Marega Ramiro Marcus

  2. Methodology • Delimitation and discretization of study area. • Determination of hydraulic parameters. • Determination of effective rainfall. • Obtaining the storm design. • Modelation with the SWMM program. • Modification to the drainage system.

  3. Study Area- “La Riereta” Basin • Total area: 17.99 Hectares • High percentage of impervious areas • Combined sewer system • Circular Sections • Concrete

  4. Discretization of basin • Total Sub basins: 18 • Basin Roughness: 0.0015 • Conduit Roughness: 0.01

  5. Calibration Fidel event Determination of effective rainfall PT=PE+PP For the cablibration the N impervious was changed to 0.0015 and also the time steps.

  6. ValidationJordi and Martina Event Jordi Event Martina event

  7. Design Torment • T= 10 Años • D= 1 Hora

  8. Problems in the drainage system

  9. Problems in the drainage system

  10. Solution Proposal

  11. Solution Proposal Tiempo de inundación N-31 15 min Tiempo de inundación N-33 55 min Tiempo de inundación N-31 1 min Tiempo de inundación N-33 1 min Area 1

  12. Solution Proposal Flooding time:12 min Floodingtime:1 min Area 2

  13. Solution Proposal Tiempo de inundación 5 min Tiempo de inundación 2 min Area 3

  14. Conclusion • Flooding succesfullycontrolledwiththeproposedalternatives. • New drainagesystemlarger and more expensivethanthecurrentsystem. • Spots with flooding ocurring for a minimum time • Integration of various techniques in order to minimize costs and impacts of drainage works in urban areas