Estimating Hip Roofs

Estimating Hip Roofs. Estimating Hip Roofs- Rafters. Pitch = 24⁰. Note – Change of Layout of Ceiling Joists to Accommodate Creepers. Determine No of Rafters. 12 500/ 600 = 20.833 = 21 + 1 = 22 Rafters each side = 44. Determine Rafter Length Span = 6900.

Download Presentation

Estimating Hip Roofs

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Estimating Hip Roofs

  2. Estimating Hip Roofs- Rafters Pitch = 24⁰ Note – Change of Layout of Ceiling Joists to Accommodate Creepers Determine No of Rafters 12 500/ 600 = 20.833 = 21 + 1 = 22 Rafters each side = 44

  3. Determine Rafter Length Span = 6900

  4. Determine Rafter Length Span = 6900 Half Span = 3450

  5. Determine Rafter Length Span = 6900 Half Span = 3450 Plan Length = 3450 3450

  6. Determine Rafter Length Span = 6900 Half Span = 3450 Plan Length = 3450 Pitch = 24° 3450

  7. Determine 1m triangle Hip Length per 1m of Rafter Rafter Length/m Rise/m 24° 1.000 Plan Length per 1m of Rafter

  8. Determine 1m triangle • Solve Common Rafter Hip Length per 1m of Rafter 1.000 ÷ Cos 24° 1.000 x Tan 24° 24° 1.000 Plan Length per 1m of Rafter

  9. Determine 1m triangle • Solve Common Rafter 1.094 0.455 1.000

  10. Determine 1m triangle • Solve Hip Hip Length per 1m of Rafter 1.094 0.455 24° 1.000 Plan Length per 1m of Rafter

  11. Determine 1m triangle • Solve Hip √(2 + Rise2) 1.094 0.455 24° 1.000 √2

  12. Determine 1m triangle • Multipliers This is the multiplier for the Hip Rafter This is the multiplier for the Common Rafter 1.486 1.094 0.455 24° 1.000 1.414

  13. Determine 1m triangle • Multipliers This is the multiplier for the Hip Rafter 1.486 1.094 0.455 24° 1.000 1.414

  14. Rafter Multiplier = 1.094 Hip Multiplier = 1.486 Determine Rafter Length Span = 6900 Plan Length = 3450

  15. Rafter Multiplier = 1.094 Hip Multiplier = 1.486 Determine Rafter Length Span = 6900 Plan Length = 3450 Plan length Eaves = 600

  16. Rafter Multiplier = 1.094 Hip Multiplier = 1.486 Determine Rafter Length Span = 6900 Plan Length = 3450 Plan length Eaves = 600 Total Plan Length = 4050

  17. Rafter Multiplier = 1.094 Hip Multiplier = 1.486 Determine Rafter Length Span = 6900 Plan Length = 3450 Plan length Eaves = 600 Total Plan Length = 4050 Rafter Length = 4050 x 1.094

  18. Rafter Multiplier = 1.094 Hip Multiplier = 1.486 Rafter 90 x 45 Determine Rafter Length Span = 6900 Plan Length = 3450 Plan length Eaves = 600 Total Plan Length = 4050 Rafter Length = 4050 x 1.094 = 4433 + Plumb Cut 100 if < 100 else Rafter Depth

  19. Rafter Multiplier = 1.094 Hip Multiplier = 1.486 Rafter 90 x 45 Determine Rafter Length Span = 6900 Plan Length = 3450 Plan length Eaves = 600 Total Plan Length = 4050 Rafter Length = 4050 x 1.094 = 4433 + 100 100 if < 100 else Rafter Depth

  20. Rafter Multiplier = 1.094 Hip Multiplier = 1.486 Rafter 90 x 45 Determine Rafter Length Span = 6900 Plan Length = 3450 Plan length Eaves = 600 Total Plan Length = 4050 Rafter Length = 4050 x 1.094 = 4533

  21. Estimating Sheet

  22. Estimating Hip Roof - Ridge Pitch = 24⁰ Overhang 450 Rafter 90 x 45 F7 600 c to c Ridge 140 x 19 Purlin 90 x 70 F7 Ridge Runs Between Crown End 12.500 -2 x 3450 = 5600 5300 + ½ Rafter Thickness for each hip end 5300 + 45 =5645 mm

  23. Estimating Sheet

  24. Estimating Hip Roof – Hip Rafter

  25. Rafter Multiplier = 1.094 Hip Multiplier = 1.486 Rafter 90 x 45 Hip 140 x 19 Determine Rafter Length Span = 6900 Plan Length = 3450 Plan length Eaves = 600 Total Plan Length = 4050 Hip Length = 4050 x 1.486

  26. Rafter Multiplier = 1.094 Hip Multiplier = 1.486 Rafter 90 x 45 Hip 140 x 19 Determine Rafter Length Span = 6900 Plan Length = 3450 Plan length Eaves = 600 Total Plan Length = 4050 Hip Length = 4050 x 1.486 = 6.018 + Hip Depth

  27. Rafter Multiplier = 1.094 Hip Multiplier = 1.486 Rafter 90 x 45 Hip 140 x 19 Determine Rafter Length Span = 6900 Plan Length = 3450 Plan length Eaves = 600 Total Plan Length = 4050 Hip Length = 4050 x 1.486 = 6018 + 140

  28. Rafter Multiplier = 1.094 Hip Multiplier = 1.486 Rafter 90 x 45 Hip 140 x 19 Determine Rafter Length Span = 6900 Plan Length = 3450 Plan length Eaves = 600 Total Plan Length = 4050 Hip Length = 4050 x 1.486 = 6158

  29. Estimating Sheet

  30. Estimating Hip Roof - Purlin Pitch = 24⁰ Overhang 450 Rafter 90 x 45 F7 600 c to c Tiled Roof Ridge 140 x 19 Purlin 90 x 70 F7 Spacing 2200 centres 1 Row Purlins at Centre Span Deduct ¼ span for every hip 12500 – 2 x 1725 = 9050 allow 150 for joints = 9200 6900 – 2 x 1725 = 3450

  31. Estimating Sheet

  32. Estimating Hip Roof - Struts Pitch = 24⁰ Overhang 600 Rafter 90 x 45 F7 600 c to c Tiled Roof with Flush Gable & Raking Eaves Ridge 140 x 19 Purlin 90 x 70 F7 Span 2700 Struts are Difficult to Estimate Develop a Best Guest Method Determine No Required 9.050/2700 =3.4= 4= 5 Each Side Determine No Required 3.450/2700 =1.28= 2= 3 Each Side

  33. Estimating Gable Roof - Struts Pitch = 24⁰ Overhang 600 Rafter 90 x 45 F7 600 c to c Tiled Roof with Flush Gable & Raking Eaves Ridge 140 x 19 Purlin 90 x 70 F7 Span 2700 Length = Use Rise Rise = ½ Span x Rise/m = 3450 x 0.455 = 1.569

  34. Estimating Sheet

  35. Estimating Gable Roof – Collar Ties Pitch = 24⁰ Overhang 600 Rafter 90 x 45 F7 600 c to c Tiled Roof with Flush Gable & Raking Eaves Ridge 140 x 19 Purlin 90 x 70 F7 Span 2700 Collar Ties 90 x 35 Collar Ties on Every 2nd Rafter On top of Purlins Length of Ridge / Rafter Spacing / 2 22/2 = 11+1 @ HALF SPAN 12 @ 3450

  36. Estimating Sheet

  37. Estimating Tile Quantities Pitch = 24⁰ Overhang 450 Rafter 90 x 45 F7 600 c to c Tiled Roof with Flush Gable & Raking Eaves Ridge 140 x 19 Purlin 90 x 70 F7 Span 2700 Collar Ties 90 x 35 Tiles 7 per m2 True Length of Rafter = 4433 Total Length of Building = 12800 + 2 x 450 = 13.700 Area of Roof = 4433 x 13.7 x 2 = 121.464m2 x 7 tiles per m2 = 850.249 say 851

  38. Estimating Sheet

More Related