Wates CBE Learning Build: Plant interactive www.cbelearning.com
What is needed and when? Building the new school will take place in stages Each slide gives you information about one stage Work out how long each stage will last Decide which machine is needed for which task Write down how long each one will be needed, and its weekly cost www.cbelearning.com
1. Ground work Digging away uneven ground 2 weeks THEN Levelling the surface 1 week THEN Creating a firm surface 1 week PLUS Removing waste materials During last 2 weeks Dumper: £850 Grader: £950 Excavator: £1,250 Compactor: £900 www.cbelearning.com
2. Foundations Digging trenches 2 weeks THEN Pouring concrete 1 week Dumper: £850 Grader: £950 Excavator: £1,250 Mixer: £2,000 www.cbelearning.com
3. Structure and roof Lifting steel beams into place 2-6 weeks Hydraulic crane: £6,000 Forklift: £850 Piledriver: £1,500 Hint: How could you make this 2 weeks and not 6? www.cbelearning.com
4. Landscaping Re-shape grounds 2 weeks PLUS Remove waste During re-shaping Dumper: £850 Grader: £950 Excavator: £1,250 Compactor: £900 www.cbelearning.com
Work out the time and costs Use your notes to make a simple spreadsheet Work out: - the total time for the build - how much each piece of plant will cost Use a simple formula to help you add up times and costs www.cbelearning.com