190 likes | 429 Views
An Integrated GIS approach to Municipal Pavement Management. Presented By: Jeff Steele, City of Greensburg Michael Bieberitz, GISP, HNTB Corporation. An Integrated GIS approach to Municipal Pavement Management. Here’s the Problem: The city of Greensburg Streets Department needed a way to:
E N D
An Integrated GIS approach to Municipal Pavement Management Presented By: Jeff Steele, City of Greensburg Michael Bieberitz, GISP, HNTB Corporation
An Integrated GIS approach to Municipal Pavement Management Here’s the Problem: The city of Greensburg Streets Department needed a way to: • Determine if the same streets were being paved more often than necessary. • Track historic project and material costs. • Estimate future project costs from assumptions based upon user input. (currently, this is done manually through a paper-based system.) Intro
City has a great GIS resource in use by some of other departments called GLANCE+ GLANCE+ Already in use by the city departments for several purposes
Sanitary GLANCE+
Water Utilities GLANCE+
Stormwater GLANCE+
The Challenge • Develop a way to display and track projects from many years that can exist on the same piece of pavement. • Use existing GIS layers wherever possible. • Incorporate new street application into existing GLANCE+ The Challenge
Challenge: How do we get so many projects to live on the same piece of road? • Data Storage • Display • Solution: cross-reference table. The Challenge
What We Learned Along the Way • Challenge: Greensburg centerline file • Street segments generally stretch from intersection to intersection. • City discovered that many past projects didn’t extend entirely from intersection to intersection. How do we get an accurate cost estimate? • Solution: split lines into smaller segments. TheChallenge
Challenge: Splitting segments causes other problems. • Sometimes the entire segment is already part of another project. • Solution: Track split segments so they can be related to each project. The Challenge
What Does the application Look Like? • Select road segments on a map The Solution
Enter a few variables: • Width • Asphalt Cost • Historic prices of asphalt are also kept. • Utilities that could affect project costs The Solution
Form returns values for • Estimated tonnage • Estimated tack cost • Estimated total cost The Solution
Results • City entered projects from last five years to test accuracy of the product • Actual cost and tonnage of material used versus what software estimated • 130 projects completed between 2000 and 2005 Results
Summary Results for all 130 Projects • Average Tack Coat Tonnage Used: • Estimated: 234.08 • Actual: 221.90 • Difference: +12.18 • % Difference: 5.4% • Average Project Cost: • Estimated: $8605 • Actual: $8095 • Difference: +$510 • % Difference: 6.3% Results
Findings: • Costs are a little inflated because centerline file stretches from center of intersection to center of intersection. • Projects are usually edge to edge, so we overestimate by about 5%. • Only 17 segments of road (totaling 1.22 miles) were paved more than once in the last five years. Results