1 / 36

200 Minuteman Drive

200 Minuteman Drive. New Design for Additional Floors and Vibration Sensitive Equipment. Brent Ellmann Structural Option Dr. Linda Hanagan - Consultant. Project Players. Owner- Brickstone Properties Architects-Burt Hill Kosar Rittleman Associates

amartino
Download Presentation

200 Minuteman Drive

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 200 Minuteman Drive New Design for Additional Floors and Vibration Sensitive Equipment Brent Ellmann Structural Option Dr. Linda Hanagan - Consultant

  2. Project Players • Owner- Brickstone Properties • Architects-Burt Hill Kosar Rittleman Associates • Structural Engineers- Atlantic Engineering Services • MEP Firm- H. F. Lenz Co. • C M Firm- Gilbane Building Company • Geotechnical Firm- Miller Engineering and Testing, Inc.

  3. Existing Building Conditions • Location: Andover, MA • 3 stories with 260,000 square feet of office space • Cost: $15 million

  4. Existing Structure • Composite floor system • K joist roof framing • Square footings and strip footings • Braced frames PICTURES

  5. Existing Mech./Elec./Arch. • Mechanical • 6 air handling units with DX cooling coils (25,000 CFM) and ducted supply with a plenum return VAV system • 2 cast iron- sectioned boilers (Gross Output – 2103 MBH) • Electrical • Main switchboard is a 480 Volt/2500 Amp switchboard • Typical light is a three tube FO32/T-8 fluorescent fixture • Architectural • Insulated metal panels, with low-E reflective glazing, along the curved northern façade • Southern facing wall is a limestone veneer

  6. Goals of New Design • Maintain owner’s original wishes while adding additional floors • All steel building • Open office plan to allow for future tenant changes • Improve performance of floor under vibration excitement due to walking for sensitive equipment • Allow for varying use of building by multiple tenants at once

  7. General Work Completed • Structural (Emphasis) • Floor Vibration Study • Column Design • Foundation Design • Braced Frame Design • Foundation Design • Mechanical (Breadth) • Increased Air Handling Capacity • Duct Sizing • Electrical (Breadth) • Increased switchboard capabilities • Increased direct feed to mechanical equipment

  8. Presented Information • New Building Height and Floor Determination By Code • Brief Overview of Mechanical and Electrical Design • Floor Design for Sensitive Equipment • Column Design • Braced Frame Design • Foundation Design

  9. Original Building • 14’-7” floor to floor height • Roof Height??? • 10’-0” tall clerestory • 2 Mechanical Penthouses

  10. New Design • Floor to floor heights???? • 10’-0” clerestory maintained • New Building height • Under code height

  11. New Design Elevation New Building Size: ####### Square Feet

  12. Mechanical Design • New Requirements • New Equipment Sizes and Numbers • New Duct Sizes

  13. AHU Locations

  14. Electrical Design • New Requirements • New Switch Board Sizes and layouts

  15. Structural Design • Floor Vibration Study • Column Design • Braced Frame Design • Foundation Design

  16. Floor Vibration Criteria • Goal: Allow for a variety of technology and research based companies to use this facility. • Design carried out using Design Guide 11 and the development of a spreadsheet

  17. Compared Systems Original System Original System

  18. Comparison

  19. Floor Vibration Conclusions

  20. Column Design • 2 Types of Columns • Columns with mechanical equipment on top • Columns without mechanical equipment on top

  21. Typical Columns Mechanical Column Non-Mechanical Column

  22. Column Splices • Splices located three feet above floor level of 3rd floor

  23. Braced Frame Design • Structure is located in a zone of high seismic activity • Earthquake forces govern lateral resisting system design Wind Loads Earthquake Loads

  24. Frame Locations

  25. Critical Frames

  26. Critical N-S Frame • Columns: • Braces: • Beams:

  27. Critical E-W Frame • Columns: • Braces: • Beams:

  28. Foundation Design • Square footings used under columns and strip footings used around perimeter of building • Engineered soil placed under footings • Compressive Strength = 6,000 psf • 3,000 psi concrete used for all footings

  29. Non-Mechanical Footings

  30. Mechanical Footings

  31. Critical Frame Footings

  32. Uplift Force • Problem: • Earthquake forces develop large uplift on footings • Solution: • Grade Beam attaching to other footings

  33. Grade Beam • 3’-0” x 5’-0” beam spanning over four square footings • Reinforcement!?!?!?!?!?!

  34. Grade Beam Positioning

  35. Conclusions

  36. Thank You

More Related