150 likes | 309 Views
Minuteman Vocational Technical Regional High School Progress. May 20 th 2019 – June 17 th 2019. June 17 th View of Area A+B – Upper Level Bathroom finishes substantially complete; toilet partitions, accessories and fixtures. June 17 th View of Area A+B – Lower Level
E N D
Minuteman Vocational Technical Regional High School Progress May 20th 2019 – June 17th 2019
June 17thView of Area A+B – Upper Level Bathroom finishes substantially complete; toilet partitions, accessories and fixtures. June 17thView of Area A+B – Lower Level Flooring materials substantially complete. Testing and Balancing of Mechanical Equip in progress.
June 17thView of Area G – Exterior Both Greenhouses in progress with exterior wall and roof glass installation.
June 17thView of Area D – Upper Level Typical classroom on floor substantially complete June 17thView of Area D – Lower Level Ceramic wall tile substantially complete. Ceiling grid in progress, MEP devices to follow.
June 17thView of Area D – Gymnasium Wood Gym floor court lines and logos complete. Final coats of sealer in progress, vented base installation to commence Wednesday.
June 17thView of Area E – Upper Level Skylight openings complete and painted. June 17thView of Area E – Upper Level Ceiling tile installation in Media Center complete. VCT Flooring in classrooms & offices complete.
June 17thView of Area E+F – Cafeteria Painting substantially complete. Ceiling tile installation in progress. Ceramic wall tile in progress
June 17thView of Area F – Lower Level Millwork installation in progress. Plumbing fixtures installation in progress. Epoxy floor in Kitchen complete. Setting of Kitchen Equipment in progress.
June 17thView of Area C – Theater Installation of fire curtain system complete. Counterweight rigging system in progress. June 17thView of Area C – Band & Chorus Millwork & Casework installation complete. VCT Flooring installation in progress.
June 17thView of Area A+B – West Roadway Loam and seed of drainage swale complete. Perimeter roadway asphalt binder complete.
June 17thView of Faculty Parking Lot - South Asphalt binder complete. Setting of curb & concrete sidewalk placement in progress.
June 17thView of Faculty Parking Lot–North Asphalt binder complete. Setting of curb & concrete sidewalk placement in progress.
June Construction Schedule Look Ahead: Area A+B & G • Complete Testing & Balancing of Mechanical Units – Area A+B Remain, Area G completed as of this update • Complete Concrete Sealant of Shop Floors • Continue Punchlist Process Area D • Complete floor finish on Gymnasium floor • Commence Wall Pad, Bleachers and Scoreboard installation • Commence Testing & Balancing of Mechanical Units. Unit feeding the Gymnasium previously completed • Commence Punchlist process Area E • Complete Classroom/Office Flooring Installation on Lower Level • Complete Millwork installation in Media Center and Lower Level • Commence Corridor flooring Installation on Upper & Lower Level Area F • Complete Installation of Ceramic Wall Tile • Complete with installation of Millwork • Continue with installation & connections of Kitchen equipment Area C • Complete Mechanical Hoist Rigging Installation • Complete Flooring activities in Band & Chorus Area • Continue Counterweight & Guidewall Rigging Installation • Commence Testing & Balancing of Mechanical Unit that feeds Band & Chorus Exterior/Sitework • Continue installation of granite curbing in faculty parking lot • Continue with placing concrete sidewalks and speed tables • Continue with landscaping plantings at perimeter of site • Continue with fill & utility installation in the Student parking lot