1 / 15

NPCC – A-2

NPCC – A-2. Presented to the NYSRC-RRS. Dr. Mayer Sasson Transmission Planning Consolidated Edison of New York June 1, 2006. Purpose.

amato
Download Presentation

NPCC – A-2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NPCC – A-2 Presented to the NYSRC-RRS Dr. Mayer Sasson Transmission Planning Consolidated Edison of New York June 1, 2006

  2. Purpose • NYISO stated to the NYSRC EC that in its work on the Comprehensive Reliability Planning Process (CRPP) it found that its rules where less stringent than those of the NPCC (A2 Criteria) and they where therefore going to follow A-2 • EC asked RRS to conduct a review and report back at its June meeting • This presentation to RRS is intended to review NPCC Criteria document A-2, especially in relation to • Conditions for the calculation of normal and emergency transfer limits • Determination of which limits are used in LOLE studies • The purpose of reviewing the NPCC A-2 criteria is be to serve as a basis for conducting the RRS review of the NYSRC rules • NYSRC reliability rules must be consistent with, but can be more stringent or more detailed than, those of NERC and NPCC, but never less stringent or inconsistent

  3. NYISO Comprehensive Reliability Planning Process • Reliability Needs Assessment (RNA) • Purpose of RNA: Ensure that all NYSRC reliability rules are observed throughout the horizon period • Ten year horizon • Defined assumptions on future facilities • Transfer limits determined for system to meet all transmission design criteria • Determine transfer limits used in LOLE calculations • Needs defined by years in which NYCA LOLE > 0.1 • Responsible TO(s) assigned • Responsible TO backstop solutions proposed • Comprehensive Reliability Plan (CRP) • NYISO acceptance of proposed backstop solutions • NYISO evaluation of impact on transfer limits and LOLE • After NYISO verification that system will meet all NYSRC reliability rules, NYISO issues CRP

  4. Present Review of NPCC A-2 and NYSRC Reliability Rules • Review NPCC A-2 to clarify • Conditions for determination of normal and emergency transfer limits • Use of normal and emergency transfer limits • Limits used in LOLE studies • Review of NYSRC Reliability Rules • Adherence to NPCC A-2 • Clarity

  5. NPCC A-2 Section 3: General Requirements • Basic Criteria are not necessarily applicable to those elements that are not part of the bulk power system or in portions of the system where instability or overloads will not jeopardize the reliability of the remaining bulk power system

  6. NPCC A-2 Section 3: Resource Adequacy – Design Criteria • Area probability of disconnecting firm load due to resource deficiencies < 0.1 years • Due allowance for demand uncertainty, scheduled outages, forced outages, assistance over interconnections from neighboring regions, (emergency?)transmission transfer capabilities and capacity and/or load relief from available operating procedures

  7. NPCC A-2 Section 4: Resource Adequacy – Operating Criteria • Each area shall have procedures in place to schedule outages such that available resources meet area’s forecasted load plus reserves requirements

  8. NPCC A-2 Section 5: Transmission Design Criteria • Applies to the bulk power system of each area • Applies after the loss of any critical facility, assuming area generation and flows have been adjusted by use of 10-minute reserves, PARs and HVdc control

  9. NPCC A-2 Section 5.1: Stability Assessment • Stability shall be maintained during and following the most severe of the following contingencies • 3-phase fault with normal clearing • Simultaneous phase-to-ground faults on two phases on a multiple circuit tower with normal clearing • Phase-to-ground fault with delayed clearing • Loss of any element without fault • Phase-to-ground on a circuit breaker with normal clearing • Loss of both poles in a DC facility without a ac fault • Failure of circuit breaker to operate when initiated by an SPS

  10. NPCC A-2 Section 5.2: Steady State Assessment • Adequate reactive power shall be installed in each area to maintain voltages within normal limits for pre-contingency conditions, and within emergency limits for all post-contingency conditions listed in 5.1 • Flows shall also be within normal limits for pre-contingency conditions, and within emergency limits for all post-contingency conditions listed in 5.1

  11. NPCC A-2 Section 6: Transmission Operating Criteria • Individual areas shall be operated in a manner such that the contingencies noted in Sections 6.1 and 6.2 can be sustained and do not adversely affect other areas

  12. NPCC A-2 Section 6.1: Normal Transfers • Pre-contingency voltages and flows shall be within normal limits • Stability of the bulk power system shall be maintained following the most severe contingencies listed in 5.1 with due regard to reclosing • Voltages must be maintained within normal limits pre-contingency and within applicable emergency limits for all contingencies listed in 5.1

  13. NPCC A-2 Section 6.2: Emergency Transfers • When firm load cannot be supplied within normal limits, transfers may be increased to the point where pre-contingency voltages and flows are within applicable emergency limits, provided that, • Stability of the bulk power system is maintained following the most severe contingency a. and d. of the list in 5.1 (certain single element contingencies) • Voltages and flows shall be within applicable emergency limits for same contingencies

  14. Transfer Limits Used in LOLE Calculations • Since • Design LOLE calculations measure probability of disconnection of firm load (Section 3) • And • Transfers are allowed to increase to emergency limits prior to the disconnection of firm load (Section 6.2) • Therefore, • LOLE calculations (RNA/CRP and IRM/LCR ) must use emergency transfer limits as defined in Section 6.2 • The NYSRC rules also require the same • Observation: • Emergency transfer limits are the emergency thermal limits unless limited by post-contingency stability and violation of emergency low voltage limits (Section 6.2)

  15. Conclusions • The NYSRC rules were written to be consistent with, and not less stringent than, NPCC A-2 • The entire Table A-1 (identical to the list in 5.1 of A-2) contingencies apply to the calculation of normal limits while only contingencies listed under “a” and “d” apply to the calculation of emergency transfer limits • Emergency transfer limits must be used in all LOLE studies, such as in the RNA and in the IRM/LCR studies • NYSRC rules in Sections on Planning (Design), Operations and Resource Adequacy need to be reviewed by RRS to meet the task assigned by the EC

More Related