1 / 11

Collector Well Presentation

Collector Well Presentation. Kyle Goodmanson, Director of Environmental Services, City of Yankton Steve Quail, Project Engineer , HDR Jim Adrian, Architect, HDR. Collector Well. Drilling and testing completed in December 2013 Water quality analysis completed February 2014

Download Presentation

Collector Well Presentation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Collector Well Presentation • Kyle Goodmanson, Director of Environmental Services, City of Yankton • Steve Quail, Project Engineer , HDR • Jim Adrian, Architect, HDR

  2. Collector Well • Drilling and testing completed in December 2013 • Water quality analysis completed February 2014 • Collector Well and Raw Water Main Design In Progress Projected Collector Well Production • Winter > 12 MGD • Summer > 18 MGD • Initial Pumping Design = 12 MGD Operating the Collector Well and the 2 Nebraska Wells, Yankton will have the ability to produce more than 16 MGD in winter and more than 22 MGD in the summer Collector Well Location Collector Well Rendering

  3. Concept #1

  4. Concept #2

  5. Concept #3

  6. Landscape Concept (Overview)

  7. Landscape Concept (Detail)

  8. Collector Well Timeline • Radio Path Study: Complete • Design Concept Report: June 23, 2014 • 30% Design Review: July 2, 2014 • 90% Design Review: August 15, 2014 • Final Design Submittal: August 29, 2014 • Advertise for Bids: September 19, 2014 • Bid Opening: October 15, 2014 • Award Recommendation: October 21, 2014 • City Commission Award: October 27, 2014 • Collector Well Startup: August 1, 2015

  9. Raw Water Transmission MainTimeline • Preliminary Design Report August 1, 2014 • 30% Design Review September 10, 2014 • 90% Design Review December 10, 2014 • Final Design January 30, 2015 • Bid Advertisement February 20, 2015 • Bid Opening March 26, 2015 • Award Recommendation: April 1, 2015 • City Commission Award: April, 13, 2015 • Substantial Completion: August 1, 2015 • Final Completion: August 14, 2015

  10. Pilot Study Timeline • Pilot Plant Setup: May 12, 2014 • Pilot Plant Completion: June 20, 2014 • Pilot Study Report: July 18, 2014 • Review with DENR: Week of July 28, 2014

  11. Water Treatment Plant Timeline • Design Workshop • Meeting #1 July 9, 2014 • Meeting #2 July 23, 2014 • Meeting #3 August 13, 2014 • City Commission Presentation August 25, 2014 • Preliminary Design Report September 11, 2014 • 30% Design Review January 9, 2015 • 60% Design Review May 8, 2015 • 90% Design Review August 14, 2015 • Final Design September 18, 2015 • Bid Advertisement October 26, 2015 • Bid Opening December 3, 2015 • Award Recommendation: December 8, 2015 • City Commission Award: December 14, 2015 • Water Treatment Plant Startup: February 1, 2017

More Related