An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IRDB Status Update March 12, 2002

  2. Agenda • Accomplishments since last briefing • Where we are today • What’s left to do

  3. Accomplishments • 12/21/01: Deployed updated PV_BUDGET_MV • 12/28/01: OLTP person data in the IRDB: • ALL_PERSONS_MV • PERSON_RESTRICTED_VW (no sensitive data) • PERSON_UNRESTRICTED_VW (sensitive data) • PERSON_INVOLVEMENTS_MV • PERSON_ADDRESSES_MV • PERSON_DEGS_MV • PERSON_EXPERTISES_MV • PERSON_EMPLOYMENTS_MV • PERSON_DISABILITIES_MV

  4. Accomplishments cont’d. • 03/05/02: Sunset a “laundry list” of outdated IRDB tables, snapshots, views, and synonyms • Identified and corrected a few IRDB data quality issues • Made minor updates to IRDB schema

  5. Where We Are Today • Completed logical design for: • PV_ICD_ASSIGNMENT_MV • PV_STEM_CELL_LINES_MV • PV_AWARDS_BY_CAN_MV • PV_APPL_TRACKING • PV_GM_AWARD • PV_BUDGET_ADMIN • Pending approval: • PV_PROGRAM_ADMIN • PV_TRAINEE_ACTIVITIES

  6. Where We Are Today cont’d. • Behind schedule with PV_GRANT_PI_MV • Creation of SQL/analyzing “refresh” problems took much longer than planned • Data quality issues slowed progress • Testing took longer than planned • Technical resources stretched too thin • Ready to deploy PV_GRANT_PI_MV pending availability of disk space

  7. What’s Left To Do • Deploy PV_GRANT_PI_MV • Refresh IRDBDEV w/ full copy of IRDBPRD • Define IRDB data architecture • Determine physical design and implementation of PowerViews (Mview vs. relational view) • Develop dbms level refresh mechanism • Setup an IRDBTST instance • Mirror of IRDBPRD • Managed via the TAR process

  8. What’s Left To Do cont’d. • Automate Mview refresh process • Complete documentation • TechView Reference Manual Vol. 2 • PowerView User’s Guide • IRDB System Operations • Integrate future year by CAN data into PROJECT_VERSIONS_T and PV_AWARDS_BY_CAN_MV

  9. What’s Left To Do cont’d. • Deploy remaining views • PV_ICD_ASSIGNMENT_MV • PV_STEM_CELL_LINES_MV • PV_APPL_TRACKING • PV_AWARDS_BY_CAN_MV • PV_GM_AWARD • PV_BUDGET_ADMIN

  10. What’s Left To Do cont’d. • Deploy remaining views cont’d. • PV_PROGRAM_ADMIN • PV_TRAINEE_ACTIVITIES • PV_REVIEW • Integrate additional OLTP data: • Award details by CAN data into AWARD_DETAILS_T • Reference tables • Other business area data (TBD)

  11. Questions?