140 likes | 157 Views
Stay updated on the latest developments at the Canadian Light Source with Phase II beamlines complete, Phase III underway, new linac RF system and power supplies, along with controls and instrumentation projects.
E N D
CLS Status Update E. Matias Canadian Light Source
Layout 170.88 m circumference 2.9 GeV ~ 225-300 mADBA lattice with 12-fold period
Major Facility Projects • Complete Phase II Beamlines • Start Phase III Beamlines • New Linac RF System • New Linac &Transfer Line Power Supplies
Phase II - Under Construction B1/B2 - Indicates Bending Magnet Beamline 1 - operational in 2008 ID - Indicates Insertion Device Beamline
BMIT Licensing Controls Related: • Safety System Design (Based on IEC 61508) • Human FactorsEngineering Review
Phase III B1/B2 - Indicates Bending Magnet Beamline ID - Indicates Insertion Device Beamline 2 – CFI funded; not yet approved for construction.
EPICS Environment • IOC Hardware • Motorola 68360 Single board computers (approximately 150) • Moxa IOCs (approximately 50) • VME 64x with SIS Optical Links (approximately 25-30) • CosyLab MicroIOC (3) • Many Server Based Soft IOCs. • IOC Software • Scientific Linux or RTEMS • EPICS 3.14.6 • High level Software • EDM, • Matlab, ROOT, + assorted packages • Web Services (next week) • PLC • Modicon Momentum (approximately 40) • Siemens S7/300 (4) • Siemens S7/400 (2) • Siemens S7 F (3)
Controls and Instrumentation Development Specific Projects • Time-resolve/Single Bunch • Fill-pattern monitor (J. Vogt/J. Bergstrom) • EPICS Software (D. Beauregard) • Transverse Feedback System (S. Hu) • Upgraded timing system • Alarm Annunciation (D. Beauregard) • Beam profile analysis …… • Beamline Java Interface ….. • ScienceStudio/Remote Access …..
Fill Pattern Monitor • Complete Phase II Beamlines • Start Phase III Beamlines • New Linac RF System • New Linac Power Supplies
Funding Partners 38 supporting University Partners and growing…