80 likes | 223 Views
Melanie M. Frye Vice President, Operations and Planning September 8, 2011 Pacific Southwest Outage . Joint Guidance Committee May 30, 2013 Salt Lake City, UT. Overall Approach. WECC staff is central coordination point Significant member involvement and action
E N D
Melanie M. FryeVice President, Operations and PlanningSeptember 8, 2011 Pacific Southwest Outage Joint Guidance Committee May 30, 2013 Salt Lake City, UT
Overall Approach • WECC staff is central coordination point • Significant member involvement and action • 52 WECC activities in four broad categories • Organizational • Reliability Coordination • Operations and Planning • Compliance • 77 member activities
Key Activities Completed • 100% completion on signatories to the Universal Non-Disclosure Agreement • RC Task Force Recommendations • 3 Guidelines approved by WECC Operating Committee • Response Report addendum on January 31
Key Activities in Progress • Remedial Action Scheme modeling • Increased data sharing, including state estimator and RTCA results • Data sharing policies • Phase II of System Operating Limit Methodology • Base Case Coordination System
Key Activities in Progress • Path Operator Task Force • Enhanced education via workshops and white papers • Path rating concept • Generator acceleration controls • Bifurcation of WECC into regional entity and reliability coordination company
Melanie M. Frye Vice President, Operations and Planning mfrye@wecc.biz Questions?