AN INNOVATIVE UNDERDROUND POWER SHEME Numerical Modeling

Discover an innovative hydroelectric scheme on a small island in Portugal through detailed numerical analyses with FEM models developed at the University of Porto. The scheme includes reversible units with a 450m elevation difference between upper and lower tunnels, featuring a 5.2km tunnel, storage gallery, cavern-pumped station, and auxiliary gallery. Explore geomechanical characterization of basalt and volcanic materials and FEM models for lower reservoir stages. Analyze structural behavior, settlements, and safety factors for optimized performance.

andreaz
Download Presentation

AN INNOVATIVE UNDERDROUND POWER SHEME Numerical Modeling

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. AN INNOVATIVE UNDERDROUND POWER SHEME Numerical Modeling Bruno Correia Luis Leal L. Ribeiro e Sousa University of Porto, Portugal

  2. This presentation is related to an UPHS innovative hydroelectric scheme in a small island, Portugal. Also presents numerical analyses performed considering FEM models developed at University of Porto.

  3. The UPHS system is equipped with reversible units with a differential elevation of about 450m between an upper tunnel and a lower storage tunnel. • The repowering included the sequence of underground works: • 5.2km tunnel located at upper level • A gallery for storage with a total capacity of 40 000m3 • A cavern pumped station • An auxiliary gallery

  4. UPHS Scheme

  5. Upper reservoir • 5200 m • 40000 m3

  6. Lower reservoir • 1200 m • 40000 m3

  7. Pumped Station

  8. Auxilliary tunnel

  9. Geomechanical characterization • ZG1 • ZG2

  10. Lower reservoir

  11. Auxiliary tunnel

  12. Compact basalt Breccias Volcanic materials

  13. Stages • FEM models for lower reservoir • Phase2 – Rocscience • 4 stages

  14. 3 types of volcanic formations

  15. Conclusions

  16. Analysis of different shapes

  17. Total displacements

  18. Pumping station • High - 26 m; • width - 12 m; • length - 44 m

  19. FEM models • 11 stages

  20. Analysis of the structural behaviour

  21. Settlements at surface • Horizontal displacements at the walls

  22. Safety factor

  23. Generalized forces • a) N; b) T; c) M

  24. 3D model • Plaxis

  25. Upper tunnel

  26. 5200 m – single TBM

  27. Fall of basalt blocks

  28. Geometry

  29. Thank You