February 18, 2010. Ventura County Water and Sanitation Department. Slide 2. El Rio Sewer Project. In August 1999, the Los Angeles Regional Water Quality Control Board determined that Groundwater in the Oxnard Forebay does not meet Basin Plan objectives for pathogens and nitrogens.Continued reliance upon septic systemsIncreases risk to public healthDegrades a valuable local water resourceIn May 2001, State Water Resources Control BoardProhibited new septic systems and discharges from e1145
E N D
1. El Rio Sewer ProjectCounty Service Area No. 34El Rio MAC Meeting February 18, 2010
Reddy Pakala, Director
Water and Sanitation Department
2. February 18, 2010 Ventura County Water and Sanitation Department Slide 2
3. February 18, 2010 Ventura County Water and Sanitation Department Slide 3 El Rio Sewer Project In response to States septic system prohibition (SSP), County Board of Supervisors directed County staff to:
Move forward with a sewer project to assist the El Rio property owners to comply with the SSP
Seek grants and low-interest financing for the project.
Our Department started working on planning, design, and securing financing in 2000. Construction began in 2005.
County formed County Service Area No. 34 (CSA No. 34) in December 2005 to seek grants, low interest loans and to operate and maintain the sewer collection system
Project has three (3) components
Wastewater Treatment Plant
CSA No. 34 sewer collection system - to connect El Rio homes to the treatment plant
Work within private properties construction of private sewer lateral, connection to the CSA No. 34 sewer collection system, and abandonment of septic systems
4. February 18, 2010 Ventura County Water and Sanitation Department Slide 4 El Rio Sewer Project
5. February 18, 2010 Ventura County Water and Sanitation Department Slide 5 Wastewater Treatment Plant
In lieu of constructing a new wastewater treatment plant for the El Rio Community, County has negotiated an agreement with the City of Oxnard (City) to reserve treatment capacity at Citys Wastewater Treatment Plant for the El Rio property owners.
This agreement was approved on June 21, 2005.
City of Oxnard Wastewater Treatment Plant
31.7 MGD plant
Located at Perkins Road
Provides the needed treatment capacity for the City and for El Rio
For the treatment capacity, each property owner pays the City a Sewer Connection Fee (SCF).
$3,539/residence (fixed)
$5,537/RUE for commercial (subject to change)
CSA No. 34 secured 30-year SWRCB financing to offer an installment payment option to El Rio property owners for City SCF.
6. February 18, 2010 Ventura County Water and Sanitation Department Slide 6 Sewer Collection System
CSA No. 34 is constructing the sewer collection system in phases in the community of El Rio to connect homes/businesses to the City of Oxnard sewer system for treatment and disposal.
Construction of Phases 1, 2, 3, 4, 5A, 6, 7, and 7A have been completed.
Construction of Phases 5B, 5C, and 5D began in November 2009 and is scheduled to be completed before the end of 2011.
Cost of the sewer collection system is $35.0 million.
CSA No. 34 has secured $26.0 million in federal, state, and local grants for the sewer collection system.
Balance of the financing is through a 30-year Clean Water State Revolving Fund financing.
7. February 18, 2010 Ventura County Water and Sanitation Department Slide 7
8. February 18, 2010 Ventura County Water and Sanitation Department Slide 8
9. February 18, 2010 Ventura County Water and Sanitation Department Slide 9
10. February 18, 2010 Ventura County Water and Sanitation Department Slide 10 Work Within Private Property
Includes construction of private sewer lateral and abandonment of septic systems
Responsibility of the property owner
Requires a permit from County Building and Safety (B&S)
Requires inspection by County B&S
Estimated cost: $2,000-$8,000/property
County approved CDBG funding to provide very low-income families assistance for construction of the sewer lateral and abandonment of the septic tank.
Must meet income criteria in the grant application.
Home must be owner-occupied.
SCF payment arrangements must be completed.
11. February 18, 2010 Ventura County Water and Sanitation Department Slide 11
12. February 18, 2010 Ventura County Water and Sanitation Department Slide 12
13. February 18, 2010 Ventura County Water and Sanitation Department Slide 13
14. February 18, 2010 Ventura County Water and Sanitation Department Slide 14 EL RIO SEWER PROJECT PHASES 5A AND 6 County Building and Safety
Permit and Inspection for Work on Private Property
Obtain a Building and Safety Permit.
Before applying for a permit obtain a Sewer Will-Serve letter from the Water and Sanitation Department of the Public Works Agency
Construct a sewer lateral from home/business to the sewer lateral installed by the CSA #34 for your property.
Call Building and Safety for an inspection of sewer lateral construction within your property.
After connection to the new sewer system, abandon the septic system.
Call Building and Safety for final inspection.
15. February 18, 2010 Ventura County Water and Sanitation Department Slide 15
16. February 18, 2010 Ventura County Water and Sanitation Department Slide 16 El Rio Sewer ProjectFuture Meetings Schedule (Tentative)
17. February 18, 2010 Ventura County Water and Sanitation Department Slide 17 EL RIO SEWER PROJECT PHASE 5B If you have additional questions, or would like additional information after the meeting, please call