1. 11/4/2011 BPA TBL- NWP&CC Wind Workshop 1 Wind Energy & Electric Power Systems Workshop (NWP&CC) Most of my experience is with Large Wind projects, connected to the BPA system.
I have attended Wind conferences where NREL and NRECA have discussed small distribution connected and even smaller residential and farm connected WTG’s. There are several programs addrerssing these initiatives.
Net Metering is one of the better ways to encourage such installations.
I have recommended in meetings with OWWG that a distribution utility undertake a small 1-3MW pilot project to see what concerns there would be for PUD’s/Coop to integrate 1-10MW wind generation on distribution linesMost of my experience is with Large Wind projects, connected to the BPA system.
I have attended Wind conferences where NREL and NRECA have discussed small distribution connected and even smaller residential and farm connected WTG’s. There are several programs addrerssing these initiatives.
Net Metering is one of the better ways to encourage such installations.
I have recommended in meetings with OWWG that a distribution utility undertake a small 1-3MW pilot project to see what concerns there would be for PUD’s/Coop to integrate 1-10MW wind generation on distribution lines
2. 11/4/2011 BPA TBL- NWP&CC Wind Workshop 2 BPA Interconnection Queue: - 25+ Proposed (Study Request) - Over 4000MW’s Wind 5 Wind Projects On-Line: - Vansycle 25MW (1996) - Stateline 90MW (2001) - Condon 50MW (2001) - Klondike 24MW (2001) - Nine Canyon 48MW (2002) This part of discussion on How to get Connected to BPA SystemThis part of discussion on How to get Connected to BPA System
3. 11/4/2011 BPA TBL- NWP&CC Wind Workshop 3 Wind Map – as of 6/03
4. 11/4/2011 BPA TBL- NWP&CC Wind Workshop 4 BPA Flowgates for ATC Calc’s Flowgate (Cutplane): A constrained portion of the transmission grid.Flowgate (Cutplane): A constrained portion of the transmission grid.
5. 11/4/2011 BPA TBL- NWP&CC Wind Workshop 5 Goal of ATC Methodology Optimize Use of Transmission System
(while meeting current and forecasted long-term obligations without significant costs or increased curtailment as compared to historical levels)
Approach Flow Based
(approach to manage the network that recognizes flows over the interconnected system while eliminating weaknesses inherent in the traditional contract path model)
6. 11/4/2011 BPA TBL- NWP&CC Wind Workshop 6 Depiction of How a Single Transaction Uses Multiple Flowgates on the Internal System
7. 11/4/2011 BPA TBL- NWP&CC Wind Workshop 7 ATC Methodology Combination Power Flow with Contract Rights
(Power flow analysis and contracts methodology to produce a 20-year monthly ATC for each of nine flowgates.)
Key Assumptions/Features:
Use of Forecasted loads.
Limited Generation dispatch patterns.
Use of Power utilization factors (PUF) to determine power flows over specific flow gates.
Maintain current contract rights.
Establish Transmission Reliability Margin (TRM) for load forecast error, modeling uncertainty and operational flexibility
8. 11/4/2011 BPA TBL- NWP&CC Wind Workshop 8 What Are The Benefits of BPA’s New ATC Method? TBL now responding to those requesting long-term service (Queue Clearing).
Clearer identification of infrastructure needs (when, where new transmission needed).
Less risk of unneeded infrastructure investment.
More effective (and efficient) curtailment and redispatch.
Facilitates development of new Tariff-based products that may more fully utilize ATC.
9. 11/4/2011 BPA TBL- NWP&CC Wind Workshop 9 TBL Products Long-Term Firm Transmission
Short-Term / Non-Firm Transmission
NT contracts allow new generation added as NT Resource
New Products?
Long-Term Partial/Seasonal Firm (new)
FERC Network Interconnection (under study)
10. 11/4/2011 BPA TBL- NWP&CC Wind Workshop 10 Interconnection Queue Issues TBL must follow OATT for Interconnections
Back Log of Thermal Generation requests
Major Transmission Additions needed
Most Wind Projects Later in Queue
Many wind projects have not requested firm transmission
Wind Projects also stalled due to:
Lack of Firm Power Purchase/Sales
Excess Generation/Soft Power Market
Lack of Transmission in Some Areas
11. 11/4/2011 BPA TBL- NWP&CC Wind Workshop 11 Wind Generation Concerns Induction Machine Issues – PF Correction
Variable Generation / Voltage Regulation
Weak System (Sub-Grid) Harmonics
Ride Through Capability and System Transient Concerns (WECC Issues)
Construction Time/Timing
Scheduling /Ancillary Services
12. 11/4/2011 BPA TBL- NWP&CC Wind Workshop 12 TBL Efforts for Wind Projects Streamlined Study process for Interconnection (IFE Process)
Developed Study Strategies to Increase use of sub-grid
Local RAS (Remedial Control Scheme)
Higher Line Loading (due to 30-35% plant factor)
Intermittent Generation Consideration
Considering Tariff revisions for Intermittent Resources (new product)
Considering Sub-Grid Management to increase Sub-Grid ATC (under study)
13. 11/4/2011 BPA TBL- NWP&CC Wind Workshop 13 Questions?