1 / 31

Chapter 10

Chapter 10. J, K, & L can all begin at the same time, if you wish (they need not occur simultaneously). K. X. M. L. J. Z. C. Y. Z. Y. X. A. B. A is preceded by nothing B is preceded by A C is preceded by B. but. All (J, K, L) must be completed before M can begin. (A). (C).

anne-hays
Download Presentation

Chapter 10

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 10

  2. J, K, & L can all begin atthe same time, if you wish(they need not occursimultaneously) K X M L J Z C Y Z Y X A B A is preceded by nothingB is preceded by AC is preceded by B but All (J, K, L) must becompleted before M canbegin (A) (C) Y and Z are preceded by X Z is preceded by X and Y Y and Z can begin at the same time, if you wish AA is preceded by X and Y AA (B) (D) Activity-on-Node Network Fundamentals

  3. Network-Planning Models • A project is made up of a sequence of activities that form a network representing a project. • The path taking longest time through this network of activities is called the “critical path.” • The critical path provides a wide range of scheduling information useful in managing a project. • Critical Path Method (CPM) helps to identify the critical path(s) in the project networks.

  4. Prerequisites for Critical Path Methodology A project must have: well-defined jobs or tasks whose completion marks the end of the project; independent jobs or tasks; and tasks that follow a given sequence.

  5. Types of Critical Path Methods • CPM with a Single Time Estimate • Used when activity times are known with certainty. • Used to determine timing estimates for the project, each activity in the project, and slack time for activities. • CPM with Three Activity Time Estimates • Used when activity times are uncertain. • Used to obtain the same information as the Single Time Estimate model and probability information. • Time-Cost Models • Used when cost trade-off information is a major consideration in planning. • Used to determine the least cost in reducing total project time.

  6. Steps in the CPM with Single Time Estimate • 1. Activity Identification. • 2. Activity Sequencing and Network Construction. • 3. Determine the critical path. • From the critical path all of the project and activity timing information can be obtained.

  7. Activity Designation Immed. Pred. Time (Weeks) Assess customer's needs A None 2 Write and submit proposal B A 1 Obtain approval C B 1 Develop service vision and goals D C 2 Train employees E C 5 Quality improvement pilot groups F D, E 5 Write assessment report G F 1 Example 1. CPM with Single Time Estimate Consider the following consulting project: Develop a critical path diagram and determine the duration of the critical path and slack times for all activities

  8. D(2) G(1) A(2) B(1) F(5) E(5) Example 1: First draw the network Act. Imed. Pred. Time A None 2 B A 1 C B 1 D C 2 E C 5 F D,E 5 G F 1 C(1)

  9. D(2) ES = ? EF = ? G(1) A(2) B(1) F(5) E(5) Example 1: Determine early starts and early finish times ES=4 EF=6 ES=0 EF=2 ES=2 EF=3 ES=3 EF=4 C(1) ES=4 EF=9

  10. D(2) ES=9 EF=14 ES=14 EF=15 G(1) A(2) B(1) F(5) E(5) Example 1: Determine early starts and early finish times ES=4 EF=6 ES=0 EF=2 ES=2 EF=3 ES=3 EF=4 C(1) ES=4 EF=9 WHAT IS EF OF THE PROJECT?

  11. D(2) ES=14 EF=15 G(1) A(2) B(1) F(5) E(5) Example 1: Determine late starts and late finish times C(1) LS=14 LF=15 Duration = 15 weeks

  12. D(2) ES=14 EF=15 G(1) A(2) B(1) F(5) E(5) Example 1: Determine late starts and late finish times C(1) LS=14 LF=15 Duration = 15 weeks

  13. D(2) G(1) A(2) B(1) F(5) E(5) Example 1: Determine late starts and late finish times LS=7 LF=9 C(1) LS=9 LF=14 LS=14 LF=15 LS = ? LF = ? LS=4 LF=9

  14. D(2) G(1) A(2) B(1) F(5) LS=0 LF=2 LS=2 LF=3 LS=3 LF=4 E(5) Example 1: Determine late starts and late finish times LS=7 LF=9 C(1) LS=9 LF=14 LS=14 LF=15 LS=4 LF=9

  15. ES=9 EF=14 ES=14 EF=15 G(1) A(2) B(1) F(5) LS=0 LF=2 LS=2 LF=3 LS=3 LF=4 Example 1: DON’T WRITE DOWN, JUST TO SHOW ALL NUMBERS ES=4 EF=6 D(2) ES=0 EF=2 ES=2 EF=3 ES=3 EF=4 LS=7 LF=9 C(1) ES=4 EF=9 LS=9 LF=14 LS=14 LF=15 E(5) LS=4 LF=9

  16. NOW::: • FOR CRITICAL PATH

  17. Example 1: Critical Path & Slack G(1) A(2) B(1) F(5) ALL THAT IS NEEDED ES & LS or EF & LF I PREFER ES & LS D(2) C(1) E(5)

  18. ES=9 ES=14 G(1) A(2) B(1) F(5) LS=0 LS=2 LS=3 Example 1: Critical Path & Slack ES=4 D(2) ES=0 ES=2 ES=3 LS=7 C(1) ES=4 LS=9 LS=14 E(5) LS=4 Duration = 15 weeks

  19. Example 1: Critical Path & Slack Slack=(7-4 = 3 Wks ES=9 ES=14 G(1) A(2) B(1) LS=0 LS=2 LS=3 ES=4 D(2) ES=0 ES=2 ES=3 LS=7 C(1) F(5) ES=4 LS=9 LS=14 A CHECK TASK LS - ES CP A 0 - 0 YES B 2 - 2 YES C 3 - 3 YES D 7 - 4 NO E 4 - 4 YES F 9 - 9 YES G 14 - 14 YES E(5) LS=4 THEREFORE CP = A-B-C-E-F-G

  20. Example 2. CPM with Three Activity Time Estimates b a m

  21. Example 2. Expected Time Calculations ET(A)= 3+4(6)+15 6 ET(A)=42/6=7

  22. Duration = 54 Days C(14) E(11) H(4) A(7) D(5) F(7) I(18) B (5.333) G(11) Example 2. Network

  23. Example 2. Network ES=7 ES=21 Duration = 54 Days LS=7 LS=21 ES=32 C(14) E(11) ES=0 LS=32 LS=0 H(4) A(7) ES=36 D(5) F(7) LS=36 I(18) ES=12 ES=7 LS=25 LS=20 B (5.333) G(11) ES=0 LS=19.667 ES=5.333 LS=25

  24. THEREFORE: • CRITICAL PATH IS: A-C-E-H-I

  25. D=53 Example 2. Probability Exercise What is the probability of finishing this project in less than 53 days? p(t < D) t TE = 54

  26. (Sum the variance along the critical path.)

  27. p(t < D) t TE = 54 D=53 or - .16 p(Z < -.16) = .5 - .0636 = .436, or 43.6 % (Appendix D) Std Normal Dist. There is a 43.6% probability that this project will be completed in less than 53 weeks.

  28. Example 2. Additional Probability Exercise • What is the probability that the project duration will exceed 56 weeks?

  29. p(t > D) t TE = 54 D=56 Example 2. Additional Exercise Solution or .31 p(Z >.31) = .5 - .1217 = .378, or 37.8 %(Appendix D) Std Normal Dist.

  30. Time-Cost Models • Basic Assumption: Relationship between activity completion time and project cost. • Time Cost Models: Determine the optimum point in time-cost tradeoffs. • Activity direct costs. • Project indirect costs. • Activity completion times.

  31. CPM Assumptions/Limitations • Project activities can be identified as entities. (There is a clear beginning and ending point for each activity.) • Project activity sequence relationships can be specified and networked. • Project control should focus on the critical path. • The activity times follow the beta distribution, with the variance of the project assumed to equal the sum of the variances along the critical path. Project control should focus on the critical path.

More Related