Seismic Retrofit of the Historic North Torrey Pines Bridge. Jim Gingery, PE, GE Principal Engineer, Kleinfelder, San Diego PhD Student, University of California San Diego. Presentation Outline. The Bridge Site Conditions Earthquake Ground Motion Development
E N D
Seismic Retrofit of the Historic North Torrey Pines Bridge Jim Gingery, PE, GE Principal Engineer, Kleinfelder, San Diego PhD Student, University of California San Diego
Presentation Outline • The Bridge • Site Conditions • Earthquake Ground Motion Development • Soil-Structure Interaction Evaluations • Retrofit Strategy
North Abutment South Abutment Old River Channel Pre-Construction Circa 1930
Earthquake Ground Motion Development • PSHA and DSHA at bedrock • Seed time history selection • Rotation of seeds to principal axes • Spectral matching to FN and FP bedrock targets • Baseline correction • Site response analysis (5 soil profiles)
Acceleration Velocity RSPMatch Displacement Seeds matched to target Spectral Matching Process Target (design) Seed time histories
2 5 1 3 4
Earthquake Ground Motions 5 4 3 2 (2 directions) X (3 EQ’s) X (5 profiles) = 30 site response analyses and time histories! 1
KX Kq KZ Soil-Structure Interaction FZ = KZ*dZ
KX Kq KZ Soil-Structure Interaction 6X6 Foundation Stiffness Matrix
6X6 Stiffness Matrix for Piled Footings • Individual pile • Pile cap • Pile group • Cross Coupling • Linearization & displacement compatibility
Liquefaction Hazard at the Site • Typical (N1)60 of liquefiable layers 12+/- • Layers typically <=5 ft thick north of Bent 4 • Layers typically 5 to 12 ft thick s. of Bent 4
Project Partners City of Del Mar (owner) Simon Wong Enrg. (prime, structural) David Evans & Assc. (nonlinear FE modeling) Caltrans (review) Earth Mechanics, Inc. (peer review) Frieder Seible (peer review)