1 / 15

Colorado Springs’ ASR Program

Colorado Springs’ ASR Program. Presented by Cortney Brand Western Water Workshop, Gunnison, CO July 28, 2005. Outline. Colorado Springs’ Water System Long-Term Water Supply Plan Denver Basin Aquifers Benefits of ASR ASR Operational Concept Feasibility Investigation Long-Term Testing

annora
Download Presentation

Colorado Springs’ ASR Program

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Colorado Springs’ ASR Program Presented by Cortney Brand Western Water Workshop, Gunnison, CO July 28, 2005

  2. Outline • Colorado Springs’ Water System • Long-Term Water Supply Plan • Denver Basin Aquifers • Benefits of ASR • ASR Operational Concept • Feasibility Investigation • Long-Term Testing • Next Steps Rampart Reservoir

  3. Colorado Springs’ Water System • Serve water to approx. 410,000 people • 97% surface water (primarily snowmelt) • 3% alluvial and bedrock groundwater • Extensive network of diversions, tunnels, reservoirs, pipelines and canals • Can deliver 110,000 AF/yr from 200 miles away • Current demands of 80-90 KAF/yr, projected to be 180 KAF/yr by 2040 • includes existing and planned DSM programs

  4. Supply Systems • Local (1800’s – present) • Blue R./S. Platte (50’s) • Homestake (60’s) • Fry-Ark (60’s) • Twin Lakes (70’s) • Colorado Canal - Exchange (80’s) 3 2 4 S. Platte R. 5 Blue River Pipeline 1 Homestake Pipeline Colorado Springs Arkansas R. Continental Divide FVA Pipeline 6

  5. Long-Term Water Supply Plan • New major delivery system – Southern Delivery System (SDS) • 43-mile, 66-inch pipeline from Arkansas River • Delivery capacity of 78 MGD • Online by around 2011-12 • Bridge gap by: • Local water system improvements • Nonpotable water development & distribution • Groundwater development & ASR

  6. Colorado Springs Denver Basin Aquifers • Extensive sedimentary bedrock aquifer system • Non-renewable • Underlies ~7,000 mi2 area (40% of Colorado Springs) • Relatively low transmissivities and well yields • Colorado Springs has 15 Denver Basin wells • Delivery capacity of 3,600 AF/yr • Used for supplemental potable supply and irrigation (parks, etc.) Denver Basin

  7. Why Pursue ASR? • Unique (for Front Range) combination of surface and groundwater supplies and infrastructure • Additional water storage capacity • Leverage investment in groundwater supply infrastructure • Use off-peak capacity in treatment plants and pipelines • Bank water for future dry years • Improve sustainability of Denver Basin groundwater • Diversify water supply portfolio (risk mitigation)

  8. Treat Pipe to wells ASR Operational Concept October – April (Inject/Store) Proactively Deliver from Reservoir Storage (make space to capture spills) Inject into aquifers

  9. ASR Operational Concept May –September (recover) Disinfect Recover Water Deliver to Tanks

  10. ASR Feasibility Investigation • Conducted Fall of ’04 • Injection/recovery testing at two wells • Water sampling & analysis • Geochemical modeling • ASR water availability analysis • Used supply system Operations & Yield model to quantify “spills” • Conceptual plan for implementing ASR

  11. ASR Testing Results • Arapahoe Well • Injection rate of 500 gpm (pumping rate of 600+ gpm) • No water quality concerns • Denver Well • Injection rate of 75 gpm (pumping rate of 75+ gpm) • Potential recovered water quality concerns • Need pH adjustment Northgate Tank Site

  12. ASR Water Availability Short-term goal (5 yrs) Ultimate goal (10 yrs)

  13. Long-Term Testing • Started in July – complete in December • Objectives • Determine sustainable, long-term injection rates • Verify water quality • Determine backwash frequencies • Arapahoe Well • 500 gpm • 3 months injection • 2+ months recovery • Denver Well • 50-75 gpm • pH adjustment • 2 injection/recovery cycles

  14. Next Steps “Crawl, Walk, Run” • Evaluate long-term testing results • Operate Northgate ASR facility in 2006 • Will recovered water need to be re-treated? • Can we maintain injection rates? • Is the system easy to operate? • Develop and implement water accounting practices • Retrofit additional wells • Work toward goal of 2-3 KAF/yr capacity by 2010

  15. Questions?

More Related