nTof Civil engineering Status -21 November 2013. Contractor’s main works started on 13/05/2013: Done : Worksite installation Demolition of barrack 559 and deviation of the existing networks Earthworks Beam shaft and opening ɸ80 in the roof of the nTOF technical gallery Piles
E N D
nTof Civil engineering Status -21 November 2013 • Contractor’s main works started on 13/05/2013: Done: • Worksite installation • Demolition of barrack 559 and deviation of the existing networks • Earthworks • Beam shaft and opening ɸ80 in the roof of the nTOFtechnical gallery • Piles • Concreting works • Finishing works : waterproofing, insulation and « chape » Ongoing: • Remaining finishing works and landscaping L.A.Lopez
Somepictures of the worksfrom the last meeting: Concretingworks
Nextsteps • Completion of finishingworks (doors, painting) → November – December 2013 • Landscaping → November – December 2013 • Handover to CERN expected on January 2014 (date to beconfirmed) L.A.Lopez