50 likes | 236 Views
nTof Civil engineering Status -4 February 2014. Contractor’s main works started on 13/05/2013: Done from the last meeting : Completion of finishing works (doors, painting ) Landscaping Handover of the civil engineering package to CERN/ nTof Project on 27 th January 2014.
E N D
nTof Civil engineering Status -4 February 2014 • Contractor’s main works started on 13/05/2013: Done from the last meeting: • Completion of finishing works (doors, painting) • Landscaping • Handover of the civil engineering package to CERN/nTof Project on 27th January 2014 L.A.Lopez
Somepictures of the worksfrom the last meeting: Finishingworks: doors, painting
Finishingworks : rails for the crane, «cloche» for the dump
Nextsteps • Start of installation works (by others) → fromJanuary 27th • Completion of snagging items GS-SE: • second layer of black top and finishing of façades → March 2014 • test of ventilation doors → date to bedeteminedwith CV Important reminder Handoveris the stage where responsibility for the building is passed from the Contractor back to the Client. Importantly, the risk in the building passes back to CERN. L.A.Lopez