CW & CALO Planning. 22 October 2008. Pascal Perret LPC Clermont. Planning. Working assumption: Dismounting: 2 persons ( Sacha & Tengiz ) ~7 days/side CW soldering: 50 base/person/day 2 persons in 2008: Tengiz & Anatoli Z. Nov. 17 – Dec 19 4 persons in 2009: ?: Jan 11 – Feb 6
E N D
CW & CALOPlanning 22 October 2008 Pascal Perret LPC Clermont
Planning • Working assumption: • Dismounting: • 2 persons (Sacha & Tengiz) ~7 days/side • CW soldering: • 50 base/person/day • 2 persons in 2008: Tengiz & Anatoli Z. Nov. 17 – Dec 19 • 4 persons in 2009: ?: Jan 11 – Feb 6 • CW tests: • 100 CW/person/day • 2 persons: Irina & Pavel • Mounting: • 2 persons: Sacha & Tengiz: 2weeks/side Pascal Perret - LPC Clermont
2008 Pascal Perret - LPC Clermont
2008 Tengizcannotdismount & solder at the same time!: Additionalmanpower … Pascal Perret - LPC Clermont
2008 Irina cannot test CW, supervised bundle replacement and absent at the same time … Tengizcannotdismount & solder at the same time!: Additionalmanpower … Pascal Perret - LPC Clermont
2009 Pascal Perret - LPC Clermont
2009 Tengizcannotmount & solder at the same time!: Additionalmanpower … Pascal Perret - LPC Clermont
2009 Irina cannottake part of CW tests after installation (commissioning) Tengizcannotmount & solder at the same time!: Additionalmanpower … Pascal Perret - LPC Clermont
Planning Pascal Perret - LPC Clermont