1 / 20

WestTrans Station Access Schemes

WestTrans Station Access Schemes. Approach, Lessons Learnt, Best Practice. Glenn Higgs & Lorna Sewell | 25 March 2010. Introduction. WestTrans Partnership WestTrans Station Access Coordinator WestTrans Station Access Programme WestTrans Approach / lessons learnt from Station Access schemes

Download Presentation

WestTrans Station Access Schemes

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WestTrans Station Access Schemes Approach, Lessons Learnt, Best Practice Glenn Higgs & Lorna Sewell | 25 March 2010

  2. Introduction • WestTrans Partnership • WestTrans Station Access Coordinator • WestTrans Station Access Programme • WestTrans Approach / lessons learnt from Station Access schemes • Step one’s • Step two’s • Step three’s • Summary – main messages

  3. WestTrans Partnership

  4. WestTrans Station Access Coordinator • Station Access Coordinator since 2008 • Underspend of £400k for station access schemes in 07/08 • Day to day tasks include: • Programme / risk management • Design champion / project continuity • Advice & assistance / problem solving • Strategic prioritisation of future station access schemes • Undertake S1’s and S2’s

  5. WestTrans Station Access Schemes • 2009/10 budget: £450k – spent! Schemes Implemented (Step 3) • Hanwell Station, Ealing • Castle Bar Park Station, Ealing Schemes Developing (Step 2) • Ravenscourt Park Station, H&F • Eastcote Station, Hillingdon • Northwick Park Station, Brent • Rayners Lane Station, Harrow Schemes Initiated (Step 1) • Turnham Green Station, Hounslow

  6. WestTrans Station Access • Lessons Learnt • and Best Practice

  7. WestTrans Approach – Step One’s • ABS Guidance requirements • Not a tick in box exercise • Keep it simple • Refer back to

  8. WestTrans Approach – Step Two’s • From WestTrans experience: • Problems have arisen during the following stages: 1. Project Management 2. Data Collection / review 3. Scheme options and appraisal 4. Consultation • Best practice measures put in place…

  9. 1. Best Practice - Project Management • Issues with changing project teams / resourcing • Seven measures: • Establish project team / clear project roles • Establish what skills are required – in-house? • Project trail / project continuity / handovers • Communication e.g. within the team (Highways), to station access coordinator • Stakeholder consultation strategy • Timescales / work programme • Key milestones • Internal deadlines e.g. cabinet approvals • Implementation timescales / liaise with Highways • Risk Register

  10. Risk Register CRUCIAL - A risk register is easy to dismiss as a chore • Bespoke • Considered • Peer/ongoing review

  11. 2. Best Practice -Data Collection • Main problems: • Not undertaken • Adhoc collection • Poorly documented • Best Practice: • Tailor data collection to scheme • Review data availability, e.g.: • Previous studies • Stakeholder knowledge • Other important considerations: • Attitude surveys / public realm

  12. 3. Best Practice - Scheme Options/Appraisal • Three problems that compromise design/timescales: • Over focused on one design option • Lack of structured evaluation of options • Default CAD use • Three approaches to assist: 1. Develop a range of options: • High, medium and low intervention 2. Scheme appraisal - matrix 3. Preparing schematic/hand drawn plans

  13. Approach One: Range of Options Why develop options? • No one ‘answer’ • Options show: • cost range • effectiveness of various alternatives • Design audit trailto justify actions and decisions

  14. Approach Two: Matrix Evaluation • Evaluating scheme options against objectives • RAG system • Infer what the preferred option may be • Key tool to help you make a decision/record various factors

  15. Approach Three: Schematic Plans • Can save time / resources • Easy for stakeholders to appreciate • CAD drawings can give the message of completeness

  16. 4. Best Practice - Consultation • Insufficient consideration of consultation • Can lead to: • Programme difficulties • Design compromise • Cost implications • Early consideration of consultation should include: • Who the stakeholders are • What they might say / mitigating measures • What are their (internal) processes? • When / how often should talk to them? • Tailored consultation e.g. JIM

  17. Step Three’s • Robust work programme, risk assessment and costs • Final stage in the process • Internal / external approval should be confirmed before this stage • Seamless handover to Highways

  18. Main Messages • Importance of setting vision, aims & objectives • Consider timescales, risk and project team at the beginning and review throughout process • Communication – team and coordinator • Maintain a clear audit trail of the project • Tailor data collection and stakeholder engagement strategy • Consider scheme options and appraisal to help inform decision making and defend actions • Consider using schematic, hand-drawn plans • Ensure seamless handover from scheme development to implementation

  19. LTN 1/08 • Best practice relevant to all schemes • Generic principles coincide with the best practice recorded when we wrote LTN 1/08 Useful document!

  20. Any questions?

More Related