20130805 Crab Cavities FPC & Power Amplifiers status. Amplifiers. We have 6 x 352 MHz amplifiers 1 x 400 MHz amplifier We have started test with a first 352 MHz Due to Long Shutdown 1 no water -> on hold We will restart in September
E N D
Amplifiers • We have6 x 352 MHz amplifiers1 x 400 MHz amplifier • We have started test with a first 352 MHz • Due to Long Shutdown 1no water -> on hold • We will restart in September • We should qualify our first400 MHz amplifierbefore end 2013 • We will launch modification of3 additional 400 MHz amplifiers(4 in total) beginning 2014 SPS 352 MHz amplifier 1994-2000
Amplifiers Transmission lines Final Driver FPC Cryo module LLRF
Amplifiers • Regarding full reflection operation we need a circulator • We are in contact with suppliers, should not be a problem except some additional integration difficulties Transmission lines (WG or Coax) Final Circulator Driver FPC Cryo module LLRF
FPC vacuum side • Will be the same window for all 3 couplers • Titanium flange • AL2O3 - 99.6% disk ceramic • 3D forged OFE Copper antenna • 3D forged OFE Copper Body with Stainless Steel flanges • 2 vacuum gauge ports • OD= 62 mm • ID = 27 mm • Windows raw material under procurement • Expected by end 2013
FPC water cooled • Regarding Power levels,50 kW CW full reflection,i.e. 200 kW CW locallyinner antenna water cooled • Helicoflex 8” • OD/ID = 195/88.5 mm • 400 MHz – 137 kW • Helicoflex 9” • OD/ID = 216.7/99.4 mm • 400 MHz – 287 kW • Crab FPC antenna OD = 27 mm • Water tube • Antenna OD/ID = 27/21 mm • Water tube OD/ID=17/13 mm • CERN rule for couplers • No soldering, welding,… between water and vacuum • We will have an exception on the ceramic side End-shape EBW Water/vacuum End-shape EBW Copper/copper
End-shape antenna Quarter Wave Double Ridge 4 rods 14.5 mm rounding on the tip
Double Walled Tube • Not included in the FPC • Part of the cryomodule • Length still to be defined (regarding cryomodule design) • Cavity flanges tbcby cryomoduleteam • RF OD 62 mm tbd tbd tbd 114 mm 62 mm
Test box & WG • Test box design • completed for 4 rods • To be completed for Double ridge and forQuarter Wave • Coaxial to Waveguide transition design completed • Antenna length awaiting DT design ?
Integration • Still a lot to do, but we are confident that whatever the space available, we will be able to match with it • Key parameter is the distance between beam axis and the water inlet on the top of the waveguide • Cryomodule design must take it into account 1108 DT 2308 maximum 1200
Schedule (December 2012) 2013 2014 2015 2016 February • Cavities to be installed in SPS in December 2015 • Cryostat fully tested Q3-2015 • Cryostat fully dressed Q2-015 • Couplers available for cryostat Q1-2015 • Couplers RF processed 50 kW SW cw all phases Q4-2014 • Couplers assembled in clean room Q2-2014 onto test box • Special processes FPC + Test Box (Cleaning, Brazing, EB welding, Gold plating, Ti coating) completed Q1-2014 • All couplers + Test Box parts machined Q4-2013 • All raw material delivered Q2-2013 • All raw material ordered Q1-2013 • (common) Coupler design completed February 2013 (+ Test Box !)
Schedule August 2013 2013 2014 2015 2016 February October • Cavities to be installed in SPS in December 2015 • Cryostat fully tested Q3-2015 ? • Cryostat fully dressed Q2-2015 ? • Couplers available for cryostat Q1-2015 Q3-2015 • Couplers RF processed 50 kW SW cw all phases Q4-2014 Q2-2015 • Couplers assembled in clean room Q2-2014 onto test box Q4-2014 • Special processes FPC + Test Box (Cleaning, Brazing, EB welding, Gold plating, Ti coating) completed Q1-2014 Q3-2014 • All couplers + Test Box parts machined Q4-2013 Q2-2014 • All raw material delivered Q2-2013 Q4-2013 • All raw material ordered Q1-2013 Q2-2013 • Coupler design completed February October 2013 (+ Test Box !)
Schedule August 2013 2013 2014 2015 2016 February October • Cavities to be installed in SPS in December 2015 • Cryostat fully tested Q3-2015 ? • Cryostat fully dressed Q2-2015 ? • Couplers available for cryostat Q1-2015 Q3-2015 • Couplers RF processed 50 kW SW cw all phases Q4-2014 Q2-2015 • Couplers assembled in clean room Q2-2014 onto test box Q4-2014 • Special processes FPC + Test Box (Cleaning, Brazing, EB welding, Gold plating, Ti coating) completed Q1-2014 Q3-2014 • All couplers + Test Box parts machined Q4-2013 Q2-2014 • All raw material delivered Q2-2013 Q4-2013 • All raw material ordered Q1-2013 Q2-2013 • Coupler design completed February October 2013 (+ Test Box !) Urgent to decide the DT design
Schedule FPC key dates • 3D drawings for approval :February October 2013 • 2D drawings (EDMS): March November 2013 • Prototypes ready for tests: March December 2014 • Couplers ready for cavity assembly : December 2014 June 2015
Conclusion • Next steps : • DT definition • Launch couplers & test boxes construction • Amplifier tests • Deal with integration issues