SIERRA POINT BIOTECH PROJECT. Planning Commission, City of Brisbane Public Hearing for the Sierra Point Biotech Project December 13, 2007. PROJECT SITE. 22.8-acre site Surrounding development: Marina Office Towers Hotel. PROPOSED PROJECT. PROPOSED PROJECT.

arnaud
Download Presentation

SIERRA POINT BIOTECH PROJECT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SIERRA POINT BIOTECH PROJECT Planning Commission, City of Brisbane Public Hearing for the Sierra Point Biotech Project December 13, 2007

  2. PROJECT SITE • 22.8-acre site • Surrounding development: • Marina • Office Towers • Hotel

  3. PROPOSED PROJECT

  4. PROPOSED PROJECT • Construction of 5 office/R&D buildings • 3- and 4-stories • Total 540,185 sq. ft. • Approx. 1,800 employees • Construction of 1,799 parking spaces • 1 parking structure (6-levels, 1,047 spaces) • surface parking lots (752 spaces) • Retail liner along garage (total 15,000 sq. ft.) • Improvements to Bay Trail along shoreline • Transfer of 12,500 sq. ft. of retail space from Parcel R • Transfer of 89,815 sq. ft. of office space to Parcel 3

  5. RECOMMENDATION • Recommend to the City Council • Certification of the Final EIR • Approval of General Plan Text Amendment • Approval of Zoning Text Amendment • Continue - Design Guidelines Amendment/Transfer of Square Footage - Design Permit - Parking Modification Use Permit - Development Agreement

  6. CEQA FINDINGS EIR completed in compliance with CEQA Identification of potentially significant findings and supporting findings All impacts mitigated to a less than significant level EXCEPT Transportation and Circulation: • Sierra Point Parkway/US 101 Northbound Ramp LOS F in Cumulative Condition for AM Peak Hour • US 101 Freeway Segments - LOS Impacts in the Cumulative Plus Project Condition Summary of Project Alternatives and Identification of Environmentally Superior Alternative (Additional Retail Alternative)

  7. General Plan Text Amendment • Add “Research and Development” as a Permitted Use in the Sierra Point General Plan Subarea

  8. ZONING TEXT AMENDMENT • Permit R&D subject to performance standards • Completion of a risk analysis • Animal testing • Limited animal testing (insects, rodents, rabbits, fish, amphibians) allowed by right, subject to performance standards • Compliance with all federal, state, local requirements as well as Institute of Laboratory Animals Resources (ILAR) standards • Animal testing of primates, cats, and dogs prohibited

  9. SQUARE FOOTAGE TRANSFERS

  10. Plaza Design Concept