120 likes | 260 Views
Project Update-October 7, 2011. North Bay TMDL projects Pre 2010 Project Highlights 2010 projects 2011 projects. NB TMDL Projects. Original Request Progress. NBWA Proposal-Fall 2009. $ 1,494,142 original total request “ Implementing Sediment and Pathogen TMDLs in the North Bay”
E N D
Project Update-October 7, 2011 • North Bay TMDL projects • Pre 2010 Project Highlights • 2010 projects • 2011 projects
NB TMDL Projects • Original Request • Progress
NBWA Proposal-Fall 2009 • $ 1,494,142 original total request “Implementing Sediment and Pathogen TMDLs in the North Bay” Marin County- Richardson Bay~ $ 369,542 Napa RCD- Napa River $ 367,500 SEC- Sonoma Creek- $ 363,800 SSCRCD-Sonoma Creek-~ $ 318, 300 NBWA/ MMWD $ 75,000 In Kind- $80k
NB TMDL Progress -Start date of grant-March 10, 2010 • NBWA (MMWD) contract signed with SFEP(ABAG)-October 2010 • Sub award agreements signed October-2010->March 2011 -1st invoice-March 2010 • 1st semi-annual progress report- April 15, 2011 -2nd invoice- July 2011 Coming Up! • 2nd semi-annual report due –Oct. 15,2011 • NBWA Board briefing- Nov. 4,2011
Pre 2010 Project Highlights • CEMAR- Steelhead monitoring-$ 34k • Board Update-Dec. 2009 http://nbwatershed.org/uploads/projects/NBWA_FMP_final.pdf > funding in Prop 84 Grant-$378 k • Private Laterals –Board Update- September 2009 Legislation passed AB 741-signed by Governor July 2011 • Adapting to Climate Change: State of the Science for North bay Watersheds -NBWA Board-Dec., 2010 -> NBCAI workshop Nov. 3 and 4-Pepperwood
2010 projects • SSCRCD- Guidelines $25k-completed Sep. 2010 http://www.sscrcd.org/pdf/Slowit.Spreadit.Sinkit.vfinal.pdf • FOCMC-Multi-Media-$5 k-completed June 2011 http://www.kidsonthecreek.com/index.html • Education / Restoration TBI-STRAW $ 15k- NBWA Board – May 2010 Napa-SLEWS $ 15k-NBWA Board- May, 2011 SEC-ELI $ 15k -NBWA Board June 2011 • City of Sonoma- Rain garden- $5k-underway • BAIRWMP- $10 k-no invoice yet • Web -site Update-$4.2 k • Approved by Board- December 2010 • Complete-April 2011
2011 Project Funding Projects funded to date 1) Aquatic Invasive Species Workshop-$2k 2) KRCB Video features-$12k
AIS Workshop • U.S. Fish and Wildlife Service (USFWS) and California Department of Fish and Game (DFG) -Review Threats and Costs from AIS infestations. -Provide Training on Protocols for Prevention of AIS introductions. -Develop procedures to reduce the risk of spreading invasive species Held -June 22Marin Health and Wellness Campus in San Rafael- http://www.nbwatershed.org/conferences/pres_workshop.php $2k for lunch estimated Actual costs- $380
Know Your WatershedKRCB Video features-$12 k NBWA Request $11.9 k SCWA match $24.1K • 10 (60 - 90 seconds) video features I general north bay 1 Marin, 1 Napa, 7 Sonoma Meeting of Stakeholders- June 13, 2011 -identified concepts and tributaries Napa R, Petaluma R, Sonoma C, Novato C 1st scripts- August 2011 Rollout- January 2012
2011 Potential Projects 1) Sea Level Rise-Pilot $44 k (WQTC lead) 2) Storm water- (WQTC lead) - Early Monitoring Plan for all 3 counties to meet Phase II Permit- $30 k minimum (WQTC lead) NBWA Bd. –July 8, 2011-Phase II permit briefing 3) SSCRCD, MCSTOPPP, Napa RCD - ~ $ 43 k(?) follow up on Slow it, Spread it, Sink it 4) Repeat -Education/ Restoration- $45k- Marin, Napa, Sonoma