An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. P13671 - Garlock Expansion Joint Garlock Expansion Joint (MSDI-P13671) Systems Design Review II January 18th, 2013

  2. P13671 - Garlock Expansion Joint P13671 Members Left to Right: Allison Feinberg (Member) Sam Kulpinski (Member) Don Thompson (Member) Wayne Evans (Customer) Elspeth Ochs (Member) Joseph Harkins (Team Lead) Danny McCormick (Member) Dr. Jason Kolodziej (Faculty)

  3. P13671 - Garlock Expansion Joint Introduction to P13671 Timeframe: Winter & Spring quarter MSD Objective: Design and build rig to test Garlock Expansion joints under high temperatures and actuation until failure while logging data

  4. P13671 - Garlock Expansion Joint Project Schedule Major Dates: • Detailed Design Review (DDR): • 2012-2 Week 10 (around 2/8/13) • Imagine RIT: • May 5, 2013 • Final Presentation: • 2012-3 Week 10 (around 5/8/13) • Celebrate our success and graduation  • After Final Presentation! Link to our MS Project file: /public/Project Schedule.mpp

  5. P13671 - Garlock Expansion Joint Customer Needs

  6. P13671 - Garlock Expansion Joint Project Specifications

  7. P13671 - Garlock Expansion Joint House of Quality

  8. P13671 - Garlock Expansion Joint Risk Assessment

  9. P13671 - Garlock Expansion Joint Functional Decomposition

  10. P13671 - Garlock Expansion Joint Concept #1 Concept Generation & Selection

  11. P13671 - Garlock Expansion Joint Concept #1 • Fluid with recirculation loop

  12. P13671 - Garlock Expansion Joint Concept #2 Concept Generation & Selection

  13. P13671 - Garlock Expansion Joint Concept #2 • Fluid without recirculation loop

  14. P13671 - Garlock Expansion Joint Concept #3 Concept Generation & Selection

  15. P13671 - Garlock Expansion Joint Concept #3 • Fluid: Air • Heat Source: Incoloy 840 Tubular Heating Source • Power: 10 Watt to heat 12” EJ to 400°F • Min Size: 0.43in Dia. x 4in • Piping System • Air Accumulator • Contained Nitrogen Accumulator

  16. P13671 - Garlock Expansion Joint Linear Actuator Options • MOOG • -890 Series standard electric servoactuator • 150mm stroke, front flange mount, male rod end • Size 4: $5,900 • Size 5: $7,900 • +Motor Controller (DS2110 servodriver): $3,000-$3,300 • 150mm stroke to 300mm stroke? +$500 • THOMPSON • ECT90 Series • 6 inch stroke: (8” avail, +~$30) • Part Number:  ECT09-I09B03PB2510-0153SJ00XX • List:  $3612.73 ea • Lead Time:  4-5 Weeks (subj. to avail.) • EXLAR • TritexII AC actuator part number T2X115-0601 with a 138-30 winding • http://www.exlar.com/product_lines/23-Tritex-II-AC-Linear-Actuator • ~$4,500 • Includes controller