SiD Surface assembly. MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki (Japan). Marco Oriunno (SLAC). SID Assembly Assumptions. Maximum Permissible L oad on Road, 60 ÷ 80 tons Assembly on surface of Magnet, Solenoid, Hcals. Assembly Hall Layout Option. Baseline Orthogonal. Op.1 Parallel.

Download Presentation

SiD Surface assembly

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SiD Surface assembly MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki(Japan) Marco Oriunno (SLAC)

  2. SID Assembly Assumptions Maximum Permissible Load on Road, 60 ÷ 80 tons Assembly on surface of Magnet, Solenoid, Hcals

  3. Assembly Hall Layout Option Baseline Orthogonal Op.1Parallel Op.3C-shape Parallel Op.2C-shape Orthogonal

  4. Assembly Yard - CMS 34,000 m2 150 m Control Room Offices 140 m 25 m Gas 1 Gas 2 GHe 223 m

  5. Assembly Yard - CMS

  6. CMS Assembly Hall

  7. Handling of Large Weights CMS Lowering Start-to-End = 12 months for 11 large components < 2,000 Tons i.e. ~ 1 Heavy lift /month Endcap - 3 rings Endcap + 3 rings Barrel 5 rings

  8. ILC • SID = 3 components (2 x 2,500 T and 1 x 4,000 T) • ILD = 5 components ( 3 barrel rings and two doors) • SID+ILD Combined < CMS

  9. Surface Hall Contruction Schedule

  10. Surface Hall Contruction Schedule Ground Leveling, Pockets excavation t1=0.5 years t0=0.5 years

  11. Surface Hall Contruction Schedule Assembly Halls t1=0.5 years t0=1 year

  12. Surface Hall Contruction Schedule Platforms t1=0.5 years to=1.5 years

  13. Surface Hall Contruction Schedule Bridge cranes t1=0.5 years to=2.0 years

  14. Surface Hall Contruction Schedule Detectors construction T1=4.0 years To=6.0 years

  15. Surface Hall Contruction Schedule Shaft excavation T1=2.0 years To=6.0 years

  16. SID Assembly Workflow Tasks Transport from factories to the site Assembly Magnet Commissioning Lowering ~ 60 tons Road Transport Gantry 4,000 tons Bridge Crane ~ 200 tons ~ 50 pieces / 60 tons

  17. ILC Assembly Hall - Proposal

  18. Barrel Construction

  19. Magnet Design – Segmentation Options 12 edges 8 edges

  20. Magnet Barrel Design 30 tons Max per plate Single plate: 17 tons through 29 tons

  21. IronBarrel Yoke layout • Bolted assembly, 144 plates 200 mm thick, 40mm gap • Opportunity to make blank assembly at the factory before shipping • Preliminary Contacts with Kawasaki Heavy Industries • Plate thickness tolerance for each: 0.1mm • Plate flatness: 4mm (in a plate) • Fabrication (assembling & welding) tolerance: 2mm • Full trial assembly: capable (but need to study) 3990 tons

  22. Solenoid Assembly Total weight, 162 t Ring 2 Ring 1 DID 6 m

  23. Magnet Assembly • 60-80 tons assemblies delivered to the site and installed with 60-80 tons capacity cranes • 33 tons vacuum tanks installed in the barrel • 64 tons solenoid coils delivered to the site and vertically assembled in to a cold mass • Solenoid swiveled and inserted inside the vacuum cryostat

  24. Solenoid Coil Module 64 tons Max.

  25. Swiveling platform

  26. SID Assembly Hall 200 t crane 4,000 gantry 25 m

  27. Magnet Commissioning, Field Map

  28. Lowering Step 1, Door +

  29. Lowering Step 2, Door -

  30. Lowering Step 3, Barrel

  31. HCAL Installation, Underground Through the Horizontal Tunnel or the Vertical shaft

  32. Required Infrastructures on surface • ~ 200 metric tons bridge crane with double trolley • ~ 4,000 metric tons Gantry • One platform 25 m x 20 m with 50 m motion range • Motion system at floor for Doors and HCals • Cold box 4K for the commissioning of the Solenoid • Gas system for the commissioning of the muon detectors • Machine Shop • Adequate Storage for heavy tooling • Office space

  33. SPARE SLIDES