Lynne’s Taxis Finance Database Status Report 1. Agenda. Work completed so far Work to complete in the next phase What’s going well and why Suggestions Project changes. Completed work. Project charter drafted, approved, and signed. Completed work.
E N D
Lynne’s Taxis Finance Database Status Report 1
Agenda • Work completed so far • Work to complete in the next phase • What’s going well and why • Suggestions • Project changes
Completed work • Project charter drafted, approved, and signed
Completed work • First draft of Gantt chart and WBS completed.
Completed work • Scope statement drafted
Completed work • Project team website completed and ready for team use and updates http://www.lynnestaxis.freewebhost.co.nz/
Completed work • Requirements defined and initial system design started
Work to complete in the next phase • Continue to adjust and improve the Gantt chart and WBS • Continue to improve and define the scope statement • Continue to research and choose potential design options • Begin developing database itself
What’s going well and why? • The project team website work went well and the use of it is increasing • The team collaborated well on choosing the design and content • The team is working well on drafting project documents by suggesting and revising until a final draft is approved by all team members • Communication is also going well and attendance at meetings is great
Suggestions • Greater research into development software • Seek third party advice on best development strategy • Formalize and agree on final design and functions
Project changes • All of the team members are going to have to improve their knowledge of database construction and coding in order to achieve the deliverables of this project.
Summary • Project is on track and on time • Team working well together • Initiation and planning phases complete • Analysis and design is next • All team members are confident that this will be a successful project