An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PIP Status Report Presented by F. G. Garcia on behalf of PIP Group

  2. Shutdown 2012 Activities – Booster Status Report

  3. PIP - Booster • Booster RF Solid State Upgrade • About 50% stations have been converted to SS • (BRF[1-8] and BRF12, BRF19) • Cavity refurbishment • 5% cavity refurbished • installed 5/2/2012 Located at L17 • BRF7 cavity testing started last Friday, 6/29. • Two more cavities removed from the tunnel to be worked next • BRF5 has been moved to MI60 and the other (BRF6) remains in the tunnel. • Utilities / LCW • The candy cane and choke tubing jobs are done for now, still need a few repairs.  • The Booster LCW system schedule to be drained starting today. • Proceeding with • proceeding with • BRF valve replacements, • magnet valve replacements and • strainer installation.

  4. Shutdown 2012 Activities – Linac Status Report

  5. PIP - Linac Power Distribution L1 Transformer Upgrade and MCC • Substation • All approval drawings submitted • Testing is expected to take place August 8-10 • Delivery will occur soon after testing is completed • MCC • All approval drawings submitted • Expected arrival date of Mid to Late August • Drawings approved on 5/30/2012 • Cable • All cable delivered • Stored in LINAC • 350 MCM will be stored at warehouse until installation is closer • Panel board • Delivered • Needs to be assembled • Safety Switches • Delivered • Stored in LINAC • Cable Supports • Delivered • Stored in LINAC • Support Structures • Will be built out of unistrut • Assembly has not yet begun • Support frames will be built in house • Junction Box • Drawing is complete • Fabrication companies have yet to respond • Since only one needs to be ordered it is unlikely that a company will construct this enclosure • Will be submitting the drawing to the machine shop soon

  6. PIP - Linac Instrumentation BPM Project Scope • Update existing RF electronics with Digital electronics • FPGA, ADC, Digital Signal Processing • Long term stability • Flexibility to modify system as needed • Implement calibration system to improve long-term stability • Implement phase measurement for Time of Flight/Energy measurement • Replaced one full crate before shutdown • 6 Pickups – D02, D03, D04, D11, D72, D73, • Position, Intensity, and Phase readback to ACNET Current Status • Received first fully production board before shutdown for checkout • Found error in PCB • Require remaking 80 PCB • $5k additional cost • $10k additional cost due to parts • New PCBs in production

  7. PIP - Linac Vacuum System • Purchased two large blower stations. To be installed this shutdown • Approval to proceed with A0 dewar repair. PO written and submitted. 7835 Procurement • Purchased two new 7835 tubes • Both tubes have been received. Appropriated stored awaiting RF testing.

  8. Shutdown 2012 Activities – RFQ Status Report

  9. PIP - RFQ • RFQ energy investigation • Manufacturer making thinner rods • Independent simulations show ~5% energy loss at the extraction gap End plate removed: Preliminary measured energy = (756.5 ± 0.5) keV PRELIMINARY Current Status: Still planning to install thinner rods More adjustments on the RFQ and tests continue on efficiency and capture