An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Advanced Metering Rule Christine Wright Public Utility Commission of Texas June 6, 2007 Retail Market Workshop COMET WG Meeting

  2. Overview • Background • HB 2129 • Staff’s Goals • Requirements • Implementation

  3. HB 2129 • Metering service to be provided by transmission and distribution utilities • PUC directed to establish surcharge for advanced metering • Recover costs of deploying advanced meters to residential and non-residential customers (non-IDR) • Rates based on costs, charged to customer classes receiving the service

  4. Advanced Metering Rule • Project initiated July 2005 • Extensive consultation • Manufacturers, retail providers, utilities, customer representatives • Rule proposed for formal comments November 2006 • Reply comments January 2007 • Workshops held in February & March • Rule adopted May 2007

  5. Purpose • Benefits of AMS to utility, retail providers, and customers • Permit utilities to recover costs though surcharge • Increase reliability of network • Encourage dynamic pricing and demand response • Make better use of generation transmission and distribution • Provide more choices for consumers

  6. Applicability & Definitions • All electric utilities, except an electric utility pursuant to § PURA 39.542(d)(1), is not subject to § PURA 39.107 • Advanced Metering System (AMS): meters, associated hardware, software, communications systems, meter information networks, collects time-differentiated energy usage • Dynamic Pricing: retail pricing for electricity that varies during different times of day • Non-standard advanced meter: meter with functions in addition to AMS features in deployment plan approved by the commission

  7. Deployment • Rule does not require deployment, but PUC by separate rule could order it • Deployment consistent with rule or PUC waiver is condition for surcharge • Six months prior to deployment or as soon as practicable an electric utility needs to file: • Statement of AMS Functionality • Either a Notice of Deployment or Request for Approval of Deployment • Request for surcharge may be included

  8. Deployment Plan • Type of meter technology • Type and description of communications equipment • Systems to be developed during deployment period • Timeline for web portal development • Deployment schedule by specific area • When monthly status reports will commence • Schedule for deployment of web portal functionalities

  9. Progress Reports • Available to market on a monthly basis following filing of its Deployment plan • Number of meters installed, listed by ESI ID • Additional information can be listed but is not required: • County • City • Zip code • Feeder numbers • Other geographic identification

  10. Mandatory Functions • AMS features 25.130(g) • Sets a floor, not a ceiling • Technology requirements: • Utility shall not deploy AMS that has not been successfully installed previously • At least 500 advanced meters in North America, Australia, Japan, or Western Europe • Waiver Provision

  11. Mandatory Functions • Remote meter reading • Two-way communications • Remote connection and disconnection* • Time-stamping of meter data • Direct, real-time access of customer and retailer to meter data • Fifteen-minute data • Storage of data • Open standards and protocols • Communication with premises devices • Upgrade capability *Exception 25.130 (g)(1)(C)

  12. Meter Data Access • Capability to provide direct, real-time access to usage data to the customer and the customer’s REP: • Hourly data transmitted to the web portal on a day-after basis • Staff using a stakeholder process, as soon as practicable, subject to Commission approval, when and how 15-minute IDR data shall be made available

  13. Communications • Capability to communicate with devices inside the premises, including but not limited to: • Usage monitoring devices • Load control devices • Prepayment systems through the home area network (HAN) • Open standards and protocols • ZigBee, Home-Plug, or the equivalent

  14. Communications Slide presented by TXU ED, March 2007

  15. Settlement 25.130 (h) It is the objective of this rule that ERCOT shall be able to use 15-minute meter information from advanced metering systems for wholesale settlement, not later than January 31, 2010

  16. Cost Recovery • Surcharge to recover costs, following filing of deployment plan • Costs for customer class to be recovered from class • Surcharge recovers capital costs (and carrying costs) less expected operating cost savings • Surcharge may not exceed amount based on deploying one-third of meters each year

  17. Time of Use Schedule Commission approval of a time of use schedule (TOUS) pursuant to ERCOT protocols is not necessary prior to implementation of the new TOUS

  18. Implementation • Discussion forum https://www-1.ibm.com/QuickPlace/txprototype/Main.nsf • Continued Workshops • Implementation Proceeding • Stakeholder Process

  19. Contact Christine Wright christine.wright@puc.state.tx.us David Smithson david.smithson@puc.state.tx.us Rulemaking Project Webpage http://www.puc.state.tx.us/rules/rulemake/31418/31418.cfm