Culver City Unified School District Photovoltaic System Project Update . June 11, 2013. CCUSD Solar Project Status Update .
E N D
Culver City Unified School District Photovoltaic System Project Update June 11, 2013
CCUSD Solar Project Status Update • SCE Easement issue update: Following a site visit from the SCE regional planner SunPower received informal approval to proceed with construction as planned. SPWR is preparing to submit the official encroachment request paperwork. • Permitting Update: SunPower did not receive DSA approval on June 4th as originally scheduled. DSA was concerned about the solar arrays spanning across multiple campuses. This issue has been resolved and a new over the counter review date has been scheduled for June 18th. • Steel has been ordered and is being procured. Fabrication will begin shortly after receiving DSA approval. • Mobilization is scheduled to occur on July 1st.
CCUSD Solar Project Status Update • SunPower and CCUSD have agreed on an alternate location for the Farragut ES solar array. The garden area will no longer be covered and no trees will be removed.
CCUSD Solar Project Timeline Task Start Date Finish Date Duration System Design 3/1/13 6/14/13 70 days DSA Permitting (over the counter) 6/18/13 6/18/13 1 days Construction 7/1/13 10/18/13 80 days Mobilize, Site Prep, Lighting Demo 7/1/13 7/5/13 5 days Concrete Foundations 7/8/13 8/16/13 30 days Steel Erection 8/5/13 8/30/13 20 days PV Module Installation 9/2/13 9/20/13 15 days Lighting, Wiring, Terminations, Misc. 9/23/13 10/18/13 20 days Commissioning 10/21/13 11/15/13 20 days Test and Commission PV System 10/21/13 10/25/13 5 days Commissioning Punch List 10/28/13 11/1/13 5 days Utility Inspection and PTO 11/4/13 11/15/13 10 days CSI Reservation 11/18/13 12/20/13 25 days Submit CSI Documentation 11/18/13 11/22/13 5 days Site Inspection by 3rd Party Firm 11/25/13 11/29/13 5 days CSI Application Review and Approval 12/2/13 12/20/13 15 days CSI Reservation Incentive Checks Jan 2014 Jan 2019 5 years
CCUSD Solar Project Timeline Highlights • SunPower will submit look-ahead schedules and coordinate all construction activities with Balfour Beatty and CCUSD. • SunPower will build all three campuses simultaneously, but work will be phased to accommodate parking needs. We will delineate our work areas and maintain parking and traffic control. Construction deliveries will be scheduled and coordinated to avoid school drop off and pick up times. • All “heavy construction” (underground work, concrete work and steel erection) will take place during Summer 2013. This will minimize the impact of our construction activities when school returns in the fall. • One twelve hour shutdown will be required for electrical interconnection. Shutdown will be scheduled on a weekend or after hours. • When school begins in September 2013, construction will be limited to the areas directly beneath the arrays. Construction areas will be safely delineated with temporary fencing.