An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CA.MTV 0125 (virtual cathode) CA.MTV 0420 CA.FCU 0430 CA.MTV 0215 CA.MTV 0390 CA.BPR 0370 ITL CA.BPM 0260 CA.BPM 0380 CA.BPM 0220 CA.ICT 0210 CA.BPM 0310 CA.BPM 0240 CA.SDH 0340 CA.BPM 0410 DUMP 0450 ACS 0230 ACS 0250 ACS 0270 TBTS CA.DHG/DVG 0130 CA.DHB/DVB 0250 CA.DHG/DVG 0245 CA.DHG/DVG 0225 CA.DHG/DVG 0385 CA.DHB/DVB 0230 CA.DHG/DVG 0320 CA.DHB/DVB 0270 CA.DHG/DVG 0265 CA.QFD 0350 CA.BHB 0400 CA.SNG 0230 CA.QFD 0360 CA.SNG 0250 CA.QDD 0355 CA.SNH 0110 CA.SNI 0120 CA.VVS 0300 CA.VVS 0200 CA.VVS 0100 CA.VVS 0500 CALIFES STATUS #4-CTF3 Committee

  2. CALIFES STATUS: Mechanics/installation 1/3 Work done on week 27 Laser Beam Transportation: work completed ! - all the line is under vacuum @ 30 Torr (0.04 atm)  no leakage - change of the spring which held the lenses - completion of the protection caps on laser table Vacuum gauge near the PI table Pumping ~ in the middle of the transport line #4-CTF3 Committee

  3. CALIFES STATUS: Mechanics/installation 2/3 Work done on week 27 Observation: problem of quadrupoles positioning compared to the vacuum chamber center  the 3 quad. have been re-centered at ~±0.25mm compared to the vacuum chamber center (magnetic axis = mechanic axis) #4-CTF3 Committee

  4. CALIFES STATUS: Mechanics/installation 3/3 Remaining “mechanical” work for end of July-August • VPM#2 – CA.MTV 0420:  recovery of the piece used for mirror introduction •  important leakage detected •  new installation foreseen on week 30 • VPM#1/2/3 – CA.MTV 0215-0390-0420: •  protections necessary for superior part of VPMs chambers •  Lead shielding necessary to protect cameras from radiations • Power Phase Shifter: in klystron gallery (CERN) •  provide water arrival for the Power Phase Shifter  General vacuum test for CALIFES foreseen from week 30 or beyond ? (CERN) #4-CTF3 Committee

  5. CALIFES STATUS: Bake out temperature Following temperatures should not be exceeded during the bake out of the line between the injecting gun and the 1rst LIL section • Is a temperature monitoring foreseen during bake out ? • ICT Bergoz will not be able to tolerate an higher temperature than 100°C #4-CTF3 Committee

  6. CALIFES STATUS: Laser system Work done on week 25 and 28: • Main objective •  Installation of the Pulse Picker and test it: • with synchronisation coming from the Masterclock instead of the final fine synchronisation • Good rise and fall time have been checked  OK • “plateau”  OK, no discontinuity • transmission measured = 81% •  in agreement with measurements made in the lab in Saclay #4-CTF3 Committee

  7. CALIFES STATUS: Laser system Work done on week 25 and 28: • The lines for sensing UV beam at the output of the laser table have been installed The line sensing the profile at the output of BBO uses the same mounting and UV converter as the sensing in CLEX • No measurements in CLEX with camera (Pulse Picker + transport), due to too low UV energy (0.3nJ)  tests are reported to beginning of September • Checking of CLEX camera: signal doesn’t go up (even with a CERN camera) •  this problem has been solved ? #4-CTF3 Committee

  8. CALIFES STATUS: BPMs 1/2 Work done on week 26:  CA.BPM0220, CA.BPM0240, CA.BPM0260, CA.BPM0310, CA.BPM0380, CA.BPM0410 Frequencies and the factors of quality of the monopole and dipolar modes were measured on the 6 BPMs Example of transmission and reflexion of all modes on 1 BPM on 1 slot • Similar results from one BPM to another, and in-situ results are comparable to Saclay • in-lab measurements • Cross-talk  26dB  OK BPM #4-CTF3 Committee

  9. CALIFES STATUS: BPMs 2/2 Work done on week 26: • Electronics boxes were installed in the CLEX • In the BPMs rack (CLEX-G), the various crates and cables were installed Work planed by the end of July (week 29 or 30): • Replacement of the LEMO cables + flat cables in CLEX-G • Problem discovered with one Acqiris board (1 channel is out of order) •  board sent to Agilent company for repair (at least 4s-8s of delay min ?) •  M. Draper try to provide us another board temporary during this period #4-CTF3 Committee

  10. CALIFES STATUS: Control Command of BPMs Work done on week 26-28:  thanks to S. Deghaye’s, etc … 3/Results sent on graphic windows under JAVA ±OK 1/Readout of acqiris board signals on OASIS  OK The 6 BPMs are implemented (command of the BPMs switchs remotely from control room is not yet tested) 2/Signal processing  OK • Work planed to be completed by the end of August: • BPMs Control Command: soft written but still some difficulties for communication with the database (not updated), transfer and tests of acqiris boards to their final rack BY064-XG have to be done, with help of CERN team ?  task on critical path #4-CTF3 Committee

  11. CALIFES STATUS: Control Command and database CALIFES Missing components in Database (status on 11th July 08): • Working set  not implemented yet for: • LLRF commands • MKS30 commands • RF Timing commands • BPMs signals (CA.BPM0220,etc …) • VPMs signals (CA.MTV0215, etc …) • vacuum ? CALIFES Components already in Database (status on 11th July 08): • Working set  OK for: • RF measured signals • Solenoids (3) • Quadrupoles (3) • Dipole (1) • Correctors (14 over 18)  We need also some help to transfer/install our software on a Control Room PC #4-CTF3 Committee

  12. CALIFES STATUS: Conclusion • End of “mechanical” tasks • MTVs (Video Profile Monitors): electrical adaptation under progress and Control Command have to be done in Summer-September, with help of CERN team ? •  task on critical path • BPMs (Beam Position Monitors) Control Command: soft written but still some difficulties for communication with the database (not updated), transfer and tests of acqiris boards to their final rack BY064-XG have to be done, with help of CERN team ?  task on critical path • Transport of the UV laser beam down to the photocathode, with Pulse Picker working in specifications  energy still too low, and have decrease last week … • RF Power Phase Shifter: Specifications document re-defined and sent to the contractors for acceptation and signature (CEA would manage directly the brazing company for mode convertors  official separation of machining and brazing tasks).New order is under progress. We foresee an installation during the shutdown (beginning of 2009). #4-CTF3 Committee