An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Engineering & Construction February 5, 2019 Encina Power Station Demolition Amended CECP 07-AFC-6C Confidential

  2. Project Timing The demolition will take place in two distinct phases: • Decommissioning Phase III (Drain & Dry) Q1 2019 – Q3 2019 • Remove oils & hazardous materials / chemicals and air gap power and fuel • Conduct full abatement survey for hazardous materials • Demolition Phase IV (All above ground structures) Q1 2020 – Q4 2021 • Abatement of asbestos , lead paint, etc • Utilize available demoed concrete for backfill • Railcars used to remove recyclable materials • Turnkey Contractor to perform work

  3. Aerial View

  4. Encina Demolition Scope • Demo Permit Under Jurisdiction of CA Energy Commission • Notifications – FAA, Abatement SDAPCD • Water Supply • Ministerial Permits - wastewater, storm water, etc. • Demo stack – No implosion • 3rd party Communications (e.g., satellite dishes) Removed by 2020 Q1 • Retain Concrete Onsite for Future Fill • Demo Buildings to Grade – after Poseidon Phase I Completion • Abatement of Hazmat (asbestos, lead paint, etc.) • Fill once-through-cooling (OTC) channels & basement • Remove aboveground structures • Use rail spur for material haul out if economically feasible and approved

  5. Encina Demolition Scope (cont) • Hazardous Material assessment – Specifically for Asbestos • Abatement of Asbestos • Permit with San Diego Air Pollution Control District for Structural Demolition • Cal/OSHA Abatement Notification • Cal/OSHA Demolition Notification • CBO Issued Demolition Permit • Tank Re-Certification for demolition • Storm Water Management – Construction Storm Water Discharge (demolition) • Waste Management

  6. CEC License Conditions • AQ-SC1 Air Quality Demolition Mitigation Manager (Designate) • AQ-SC2 Air Quality Demolition Mitigation Plan • AQ-SC3 Fugitive Dust Control • AQ-SC4 Dust • AQ-SC5 Diesel Fueled Engine Controls • AQ-SC12 AQDMM Monthly Compliance Report (MCR) • AQ-SC13 No Implosion Allowed • GEN-1 CBO approval of work (CBO to Issue Demolition Permit) • HAZ-7 Security Plan • NOISE-1 Notice for Hotline Availability • NOISE-2 Public Notice of Start of Demolition • NOISE-3 Noise Control Program • NOISE-6 Noise Restriction • SOIL&WATER-2 Non-Potable Demolition Water Use Plan

  7. CEC License Conditions (cont) • SOIL&WATER-4 Demolition Wastewater Permit • SOIL&WATER-6 Temporary Water Meter Installation • SOIL&WATER-9 NPDES Permit Correspondence Reporting • TRANS-1 Traffic Control Plan • TRANS-5 Post-Construction Road Inspection • TRANS-7 Parking and Staging Plan • WASTE-5 Demolition Waste Management Plan • WASTE-6 Demolition Notification SDAPCD Form • VIS-3 Screen Demolition Site As Needed • WORKER SAFETY-1 Demolition Health and Safety Plan • WORKER SAFETY-3 Demolition Safety Supervisor • WORKER SAFETY-4 CBO Safety Supervisor • WORKER SAFETY-5 AED Device Training and Availability