An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Implementing new sextupoles Issues along the way Orbit smoothing Pbars at 150 GeV Losses in squeeze Peak vs integrated luminosity Recent Tevatron Operations Ron Moore Fermilab – Tevatron Dept.

  2. Chromaticity Correction Sextupoles • Correct 2nd order tune and β-function chromatic effects • Simulations show improved lifetimes (see previous talk by A. Valishev) • Plan – split off ¼ existing sextupole SF/SD elements for use in new circuits • Pull new cables (last long shutdown) • Run new circuits as “normal” chromaticity elements w/ new supplies (Feb 07) • New power supplies operate just fine – no failures • Turn OFF new circuits – necessary for injection, ramp, squeeze (early May) • Did major orbit smoothing as well (necessary, but added complications) • First HEP store in this configuration - # 5409 on May 3 • Difficult 2 weeks of running as we tuned up (limited proton intensities) • Accesses to change polarities of some of the new elements (May) • Necessary for low-β – that’s why we wanted to do previous step first • Studies for running new circuits @ low-β • Implement new circuits for HEP – first store # 5480 on June 7 • Ongoing evaluations and tweaks to improve performance We knew this would be tough R. Moore - FNAL

  3. Why smooth orbits? • 150 GeV central orbit • Up to 4 mm offsets! • Not good • Turning off sextupoles gives up to 0.5 mm offsets • Motivates the big smooth R. Moore - FNAL

  4. Issues @ 150 GeV After Turning OFF New Sextupoles • Losses at 150 GeV and early in ramp • Proton losses high enough to cause quenches • Requested smaller proton intensities for 1 week • Lifetimes were worse, too • New injection helix for 150 GeV and early in ramp • Improve losses and lifetimes – more separation / reduce beam-beam • Separation @ 150 GeV limited by aperture • Needed orbit bumps @ C49 to increase aperture for beams • Pbar emittance growth @ injection • Reduced peak luminosity • Found vertical tune too high → lowering solved problem R. Moore - FNAL

  5. Turn off new sextupoles + orbit smoothing Lower pbar vert tune New helix + orbit bumps R. Moore - FNAL

  6. Pbar Emittances @ Injection J. Annala R. Moore - FNAL

  7. Losses during Squeeze • Proton loss is driven by beam-beam effects • Depends on pbar intensity and emittance • Higher brightness = intensity/emittance  more proton loss • Becoming more problematic with higher pbar intensities • Orbit changes were big impact • Where the lost beam lands can be problem • Loss spikes or integrated dose @ CDF or D0 • Quenches (like those @ D11 recently @ LBSEQ 17) • Chasing losses around with orbit bumps • e.g., decrease losses at D0, increase @ D11, CDF R. Moore - FNAL

  8. Proton Losses Increase with Pbar Intensity R. Moore - FNAL

  9. Store 5426 – before D0 horz angle changes early in squeeze Low-β LBSEQ A49H Sep [kV] Proton Intensity [109] LBSEQ 17 Init Collisions High D0 losses D0 BLM [Rad/s] CDF BLM [Rad/s] R. Moore - FNAL

  10. Store 5450 – after D0 horz angle change early in squeeze Low-β LBSEQ A49H Sep [kV] LBSEQ 17 Proton Intensity [109] Init Collisions Higher CDF losses D0 BLM [Rad/s] CDF BLM [Rad/s] R. Moore - FNAL

  11. Losses @ LBSEQ 17 • Proton losses at LBSEQ 17 is not a new feature • Longstanding pain from beam-beam effects • Horz separation minimal during switch from injection to collision helix • B17 horz separator goes to 0, switches polarity • Was requirement to get pbars on correct side for Roman pots • Depends on pbar intensity and emittance • Higher brightness = intensity/emittance  more proton loss • After solving pbar emittance growth at injection, saw high losses and 2 quenches @ D11 @ LBSEQ 17 • Requested reduced pbar intensity during investigation (~1 week) • Vertical angle bumps @ D0 helped reduce beam lost @ D11 • Lowered chromaticities, too • Ready to step up pbar intensities again • Still keeping an eye on losses • Could also try developing new helix, if needed R. Moore - FNAL

  12. D11 Losses @ LBSEQ 17 Before bumps LBSEQ 17 [Rad/s] After bumps R. Moore - FNAL

  13. Fixing LBSEQ 17 Once and For All (?) • Want to eliminate the source of beam loss → maintain larger beam separation • Flip horz helix in “short arc” to eliminate B17H separator polarity change • Protons and pbars swap horz orbit positions for HEP • B11H, B17H and C49H separators run in opposite polarities • Need extensive conditioning period → end of long shutdown • No collimators to flip in short arc R. Moore - FNAL

  14. End of Squeeze • Transition from LBSEQ 24→25 (low-β) • New sextupoles come on + other associated changes (tunes, etc.) • Pbar loss and likely emittance growth • Coupling on pbar helix is large ~0.01 • Difficult to keep tunes away from resonances • Still a work in progress… • Orbit bumps can’t be explored fully since the IP positions / angles are constrained by experiments for low-β / collisions R. Moore - FNAL

  15. Pbars at End of Squeeze – Shot 5542 New sextupoles turning on Low-β LBSEQ A49H Sep [kV] Proton Intensity [109] Poor pbar lifetime Pbar Intensity [109] Init Collisions D0 BLM [Rad/s] CDF BLM [Rad/s] R. Moore - FNAL

  16. D0 Low-β Quad Motion • This interesting topic is a separate talk in its own right • Air flow / thermal gradients between Tev tunnel and collision hall causing support girder to twist, flex (?) • ~μm/~μradchanges in quads lead to ~mm changes in arcs • Recent hotter weather has led to more motion that causes significant orbit changes from shot to shot • Complicates investigation of losses & orbits in squeeze • Makes orbit smoothing difficult when quads move during shot-setup • Larger than desired D0 horz IP changes during HEP • Lattice measurements on Thursday needs to be repeated due to orbit changes over the few hour study rendered data useless • AD & D0 working together to develop new ideas to reduce motion R. Moore - FNAL

  17. D0 Low-β Quad Motion D0 Lumi [μb-1/s] D1Q3 Roll [μrad] HC49 current [amps] D0 horz IP offset [μm] Temperature [deg F] R. Moore - FNAL

  18. Chromaticities @ Low-β • Without new circuits Fit to parabola… Significantly non-linear Tune vs Frequency (Momentum) Offset • With new circuits • Much more linear! • Correct chromaticity as intended May 26 study R. Moore - FNAL

  19. Evaluating New Sextupoles R. Moore - FNAL

  20. Peak vs Integrated Luminosity • Peak luminosity is a sexy number... • …but integrated luminosity on tape is where the physics is • Yes, peak lumi is down from our record running in Jan/Feb • Let’s look further… R. Moore - FNAL

  21. Sextupole work J. Crawford’s spreadsheet R. Moore - FNAL

  22. J. Crawford’s spreadsheet R. Moore - FNAL

  23. Average lumi @ recent peak lumi is as good or better! J. Crawford’s spreadsheet R. Moore - FNAL

  24. To-Do List Before Shutdown • Understand effect on new sextupoles during HEP • More precise lattice measurements @ low-β • 2-3 hours proton-only differential orbit measurements • Tried once, need to be repeated… • Identify need for corrections, way to correct coupling on pbar helix • Pbar-only store to gather data for collision helix closure • Just a single transfer • Better than using protons and putting separators in opposite polarity • Higher risk of sparking on subsequent HEP stores and causing quench R. Moore - FNAL

  25. Summary • Implementing 2nd order chromaticity correction sextupoles has been long • New circuits turned off and orbits smoothed in early May (#5409) • New sextupoles ON at low-β only since early June (#5480) • Needed orbit smoothing has had big impact on operations, too • Attacked various problems with additional orbit bumps • Losses at 150 GeV and early in ramp • Losses during squeeze, especially LBSEQ 17 • Complicated by recent weather exacerbating D0 low- β quad motion • Peak luminosity has been down, but integrating OK • Average luminosity for recent peak lumi is as good or up to 25% better! • New sextupoles correct chromaticity as desired, but still working on other lattice corrections to improve performance • Need to fix large coupling on pbar helix R. Moore - FNAL

  26. Orbit Effect from Turning Off New Sextupoles • 150 GeV on 2/21 • Before smoothing central orbit to 0 R. Moore - FNAL

  27. R. Moore - FNAL