BACKGROUND . Project was conceived to ensure consistent supply of Phosphoric Acid for FFBL DAP plant operation. MOU signed with OCP - June 01, 2004 Project feasibility study concluded - September 2004 Shareholders agreement signed - September 14, 2004 Fauji group mobilized – January 01, 2005

avani
Download Presentation

BACKGROUND

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BACKGROUND • Project was conceived to ensure consistent supply of Phosphoric Acid for FFBL DAP plant operation. • MOU signed with OCP- June 01, 2004 • Project feasibility study concluded - September 2004 • Shareholders agreement signed - September 14, 2004 • Fauji group mobilized – January 01, 2005 • Licensors and Engineering contracts – January 14, 2005

  2. INTRODUCTION OF OCP (Office Cherifien des Phosphates) • State owned Moroccon organization established in 1920, with Head office at Casablanca • Main areas of business: • Mining and export of Phosphate rock • Manufacturing & export of Phosphoric acid & Phosphatic fertilizers • Annual Turnover- $ 2 Billion • Employees arround 20000 • Production facilities at Safi and Jorf Lasfar • Phosphate rock mining facilities at Khourigba, Youssoufia, Benguerir and Boucraa. Total reserves are ~80 Billion MeT • Joint ventures with India (IMACID & PPL), Belgium/Germany (EMAPHOS) • Joint venture with Brazilian group (BUNGE) is being negotiated

  3. PMP

  4. PROJECT SALIENT FEATURES • Sulphuric Acid Plant : 3410 MTPD (1,125,000 MTPY) • Phosphoric Acid Plant : 1135 MTPD (375,000 MTPY) • Power Plant : 32 MW • Water Treatment : 2 Demin. Trains & 3 Polishers • Infrastructure : Offsites and other facilities • Total Cost : 2030 Million MAD • Debt / Equity : 60 / 40 • Effective Date : Jan 14, 2005 • Completion time : 30 Months