1 / 14

East County Justice Center

East County Justice Center. Board Briefing June 24, 2008. Purpose. Discuss options which address space needs and budget. Original Project. Program Plan 4 courtrooms (expand to 6 in future) DA and Bldg Security MCSO (Hansen bldg replacement) City of Gresham Police

avel
Download Presentation

East County Justice Center

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. East County Justice Center Board Briefing June 24, 2008 Purpose Discuss options which address space needs and budget

  2. Original Project • Program Plan • 4 courtrooms (expand to 6 in future) • DA and Bldg Security • MCSO (Hansen bldg replacement) • City of Gresham Police • IT Disaster Recovery site (shell space only) • Project funded through the sales of disposition properties, i.e. no debt

  3. Program Options & Budget • Two options have been identified for this briefing • Common assumptions • Funding • Approaches

  4. Assumptions • We cannot sacrifice quality and durability to cut construction costs • We cannot cut space beyond what is truly needed to be functional • We must provide the needed court space • The Hansen Bldg. cannot be renovated economically • LEED Silver is a mandate • Gresham Police space must be budget neutral • We cannot consider structured parking (cost)

  5. Project Costs • Projected construction costs are based on comparable projects; they are not “cost estimates” (which requires a bldg. design) • Projected costs were agreed upon by architect, contractor, cost estimator, and FPM • Springfield, OR Justice Center was selected as the best comp; June 2007 bid was $215/sf • Escalated by 7.5% to mid-2009 = $240/sf • A contingency of 10% is included in all options

  6. Project Costs (cont.) • Site Acquisition $5.4 million Assumes woodshop property acquired • Site Costs* $2.0 million Includes parking, landscape, hardscape, demo, utilities, etc. • Soft Costs* $5.0 million Includes a long list of items including professional fees, land use and regulatory costs, LEED certification, studies & land survey, project management, FF&E, Percent for the Arts, etc.

  7. Option #1 – Courts & Gresham • 2 court sets with DA & bldg. security • Gresham Police – in future Courtroom • MCSO at Yeon • No IT space • Projected cost = $26.3 million

  8. Option #2 – Courts, Gresham, & MCSO (split ECJC/Yeon) • 2 Court sets with DA & bldg. security • Gresham Police – in future Courtroom • MCSO – in future Courtroom and Yeon (high parking and large space uses at Yeon) • No IT space • Projected cost = $27.5 million

  9. Issues for both Options • City of Gresham and/or MCSO occupy future Courtroom space at ECJC – requires future replacement space • Lose benefits between Sheriff’s Office and City of Gresham Police sharing space • Uncertain cost for probable seismic upgrade to Yeon Annex (est. $350k to $500k) • Relocate Yeon Annex functions • Relocate DCS Director’s office • Relocate Land Use Planning and Surveyor to 8000 sq. ft. modular building on the Yeon site. • IT space not in these options

  10. Funding Sources • Current - • Edgefield South $ 9.5 million Sale closed • Edgefield North $ 5.6 million $ 15.1 million Projected closing July 2008 • Gresham $ 2.0 million $ 17.1 million Assumes no change in commitment • 242nd Vacation $ 1.6 million $ 18.7 million Pending approval by Troutdale • Hansen Bldg. $ 3.5 million $ 22.2 million New appraisal in progress

  11. Budget Summary • Net identified revenue - $22.2 million (includes 242nd Ave Vacation - $1.6 million) • Budget shortfall – $4.1 million to $5.3 million based on presented options • Project revenue possibilities • Further property sales • Borrowing • One-time-only

  12. Schedule • June/July 2008 • Work with Partners to program space based on final direction • Produce Pre-Design Project budget estimate based on final programming • Early August 2008 • BCC Approval of Revised Project Plan (FAC-1)

  13. Things to consider • Timeframe for Courtroom(s) needs • MCSO and City of Gresham impacts to operations • Multiple and future move scenarios carry risk • Life cycle costs vs. upfront Capital costs • County financial situation

  14. Which Options Should We Develop? • Of the options presented, option 2 is the most promising • Other thoughts or options to explore?

More Related