1 / 4

Arlington Elementary – Renovation

Arlington Elementary – Renovation. Architect: RossTarrant Architects General Contractor: WS Construction Substantial Completion Date: August, 2010 GC Contract Sum: $9,920,194 Total Project Cost: $12,450,800 Change Orders: $36,900 (#1--Demo) Current Phase: 1 (On Schedule)

avital
Download Presentation

Arlington Elementary – Renovation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Arlington Elementary – Renovation • Architect: RossTarrant Architects • General Contractor: WS Construction • Substantial Completion Date: August, 2010 • GC Contract Sum: $9,920,194 • Total Project Cost: $12,450,800 • Change Orders: $36,900 (#1--Demo) • Current Phase: 1 (On Schedule) • Estimated Completion: 17% September 2009

  2. Arlington Elementary – Renovation Rendering of Final Façade September 2009

  3. Arlington Elementary – Renovation Work Completed in Last 30 Days: Mock up of exterior wall materials has been completed. Water detention system is in place. Joists have been set in the gymnasium and the slab is scheduled to be poured on 9/16. CMU walls continue in the kitchen. Current Work Effort (September): Demolition is almost complete. The shoring of the existing structure is in place and reconstruction of the bearing wall between existing and new construction has begun. Mechanical, electrical and plumbing work continues on site and in the existing building. Foundations continue at the main entry and in the media center. September 2009

  4. Arlington Elementary – Renovation Water Detention System New Walls for Kitchen Bearing Wall Between Old & New Construction Mechanical, Electrical Plumbing Work September 2009

More Related