50 likes | 203 Views
Work Package 2. Current status and schedule. Giacomo Grasso ENEA UTFISSM-PRONOC LEADER PCC meeting Karlsruhe, November 23, 2012. ELFR domain. Core design performed Complete core characterization completed Core data provided to WP5 (“LFR database for safety analyses”)
E N D
Work Package 2 Current status and schedule Giacomo Grasso ENEA UTFISSM-PRONOC LEADER PCC meeting Karlsruhe, November 23, 2012
ELFR domain • Core design performed • Complete core characterization completed • Core data provided to WP5 (“LFR database for safety analyses”) • Complete Thermal/Hydraulic analysis going to start • Mechanical design performed • Radiation damage analysis not yet performed • Transition from start-up to equilibrium core underway Task 2.1 Task 2.1 Task 2.1 Task 2.3 Task 2.4 Task 2.5 Task 2.1
ALFRED domain • Core design performed • Complete core characterization completed • Core data provided to WP5 (“ALFRED database for safety analyses”) • Complete Thermal/Hydraulic analysis almost done, report in progress • Mechanical design performed • Radiation damage analysis performed, finalizing the report Task 2.2 Task 2.2 Task 2.2 Task 2.3 Task 2.4 Task 2.5
WP2 timing Mil 03 Mil 09 Mil 02