An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Team 1 A & D Case

  2. MS Project Results • What is the projected completion time of the project? • Before leveling resources: 10/1/03 • After leveling resources: 11/11/03 • What is the total cost? How much is the labor and capital costs? • Labor Cost: $916,980 subject to leveling resources • Capital Cost: $98,500 • Critical Path • MS Project

  3. Will the Project Complete in Time? • There is a high risk of this project not completing on time • After leveling resources, there is very little time between project completion date and the height of the shopping season

  4. What are the risks? • If the site needs to be up by Thanksgiving Weekend, there are only ~2 weeks of additional work time available • Being unable to level all resources may cause further delays • This is not enough buffer to fully take advantage of the holiday shopping season • Due to the design phase being on the critical path, changing the scope with such a small window of extra time would not be possible.