UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 ( L.Lee ). UCN 2014 Installation: Schedule. 2. UCN 2014 Installation folded into Shutdown Schedule New schedule release today (SAS Committee) UCN SASP0184,185,186,187 Start: January 2 ; Finish: ~ April 10
E N D
UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)
UCN 2014 Installation: Schedule 2 • UCN 2014 Installation folded into Shutdown Schedule • New schedule release today (SAS Committee) • UCN SASP0184,185,186,187 Start: January 2 ; Finish: ~ April 10 • Shield-Plug reconfiguration: starts in mid-March • Work Requests (10) submitted; Not all approved yet. • Lift Plan (Jason), Alignment Plan (Dave P.), Dose Analysis (Cam RPG) • CNSC Approval of Shield Plug (“in the mail” “OK to proceed” Anne/Jeff)
UCN 2014 Installation: Personnel 3 • .T-B/L (Beamlines) • Installation/Alignment of B/L Components • Consultation w/ TRIUMF Alignment Group (D.Preddy, B.Gasbarri, M.Vogel) • D.Pearce hired on contract direct UCN alignment efforts • Hexagon Metrology Engineer (R.Molari) services contract advisory • tracker specialist • .T-Mech (Mechanical) • General removal/assembly of components • M.Goyette hired on contract • T.Hessels(UCN Designer & .T-Mech) ~ 50% (?) • Require 1 more .T-Mech(TRIUMF) 50% • Crane Crew • At start of shutdown (Jan.2 – 17) remove/excavate shielding blocks • Intermittent (Jan.21 – Mar.26) removal/placing of components • Near end of shutdown (Mar.27 – Apr.10) restoring shielding+plug • Others • Contractors: Plumbing (Lockerbie), Electrical (Entech), Coring (West Coast) • Safety/RPG, Engineering (Civil, Electrical), Plant Group Intermittent • Diagnostics & Controls 1AM5 (best efforts)
UCN 2014 Installation: Alignment Plan 4 • Alignment Plan & Logistics • Plan being developed in consultation w/ Alignment group & D.Pearce • Purchase Order for laser-tracker rental from Hexagon Metrology • Alignment Plan Overview • Fiducialize magnets, frames & other B/L components w/ Laser Tracker • - Shoot array of points (upstream/downstream) on each component • Shoot Vault & 1A monuments w/ Laser Tracker & establish coord. system • Lay down grid of new monuments (Vault & 1A tunnel) & record • - Number/Locations of new monuments (consult Bruno/Mike) • Paint floor and/or lay down scribe lines • Mark drill location (and angle) on Immovable-block for coring • Install/Locate frames (Theodolite or Laser Tracker) • Install/Align magnets/components according to schedule • - Use Laser Tracker to position fiducializedpoints
Meson Hall Clean-up 5 • M11 Cleanup Completed • Staging area for new Shielding • M13 Cleanup Completed • Staging area for “removed” blocks • Some blocks already moved to M13 • Jason’s layout for temp. block storage • “Boot-box” area for 1A access M13 • Cleanup above BL1A/1B • Almost completed (thanks to Ron K.) • 46 items removed; ~11 items left to move (this week & after beam OFF) • Catalogue of items removed: • https://ucn.triumf.ca/triumf/beamline/Catalog-MH-cleanup.pdf • Extra Blocks (6’ and smaller) stage to M13 “monolith”
Cleanup above BL1A/1B Floor Plan (SW Meson Hall) E Zone C (slides 29-59) Zone B (slides 15-28) Zone A (slides 5-14) N Gateway S W (From Dec/2012) Total number of items: 9 (zone A) + 13 (zone B) + 30 (zone C) = 52
Floor Plan (SW Meson Hall) E Zone C (slides 29-59) Zone B (slides 15-28) Zone A (slides 5-14) N Gateway S W (From Dec/2012) Total number of items: 9 (zone A) + 13 (zone B) + 30 (zone C) = 52
Floor Plan (SW Meson Hall) E Zone C (slides 29-59) Zone B (slides 15-28) Zone A (slides 5-14) N Gateway S W (Dec/2013) Objects rem. Total number of items: 1 (zone A) + 5 (zone B) + 3 (zone C) = 9(43 objects cleared)
Floor Plan (SW Meson Hall) E Zone C (slides 29-59) Zone B (slides 15-28) Zone A (slides 5-14) N Gateway S W (Dec/2013) Objects added N2 N3 N1 N4 N5 Total number of items: 1 (zone A) + 5 (zone B) + 3 (zone C) = 9+ 5 “New items”
Floor Plan (SW Meson Hall) E Zone C (slides 29-59) Zone B (slides 15-28) Zone A (slides 5-14) N Gateway S W (Dec/2013) Objects added (& removed) N2 N3 N1 N4 N5 Total number of items: 1 (zone A) + 5 (zone B) + 3 (zone C) = 9+ 2 “New items”
Remaining items to move this week Detector Group UCN R/H To M11: To Storage “Barn”: To top of M9, M11, M20 blocks: Beamlines R/H Beamlines
Remaining items to move after beam OFF To Vault Roof: PIENU Beamlines T2K/Snolab Outside M11: EWB/Beamlines