UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 ( L.Lee )

UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 ( L.Lee ). UCN 2014 Installation: Schedule. 2. UCN 2014 Installation folded into Shutdown Schedule New schedule release today (SAS Committee) UCN SASP0184,185,186,187  Start: January 2 ; Finish: ~ April 10

barid
Download Presentation

UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 ( L.Lee )

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UCN 2014 Installation Overview/Logistics UCN Monthly Meeting Dec.18, 2013 (L.Lee)

  2. UCN 2014 Installation: Schedule 2 • UCN 2014 Installation folded into Shutdown Schedule • New schedule release today (SAS Committee) • UCN SASP0184,185,186,187  Start: January 2 ; Finish: ~ April 10 • Shield-Plug reconfiguration: starts in mid-March • Work Requests (10) submitted; Not all approved yet. • Lift Plan (Jason), Alignment Plan (Dave P.), Dose Analysis (Cam  RPG) • CNSC Approval of Shield Plug (“in the mail”  “OK to proceed”  Anne/Jeff)

  3. UCN 2014 Installation: Personnel 3 • .T-B/L (Beamlines) • Installation/Alignment of B/L Components • Consultation w/ TRIUMF Alignment Group (D.Preddy, B.Gasbarri, M.Vogel) • D.Pearce hired on contract  direct UCN alignment efforts • Hexagon Metrology Engineer (R.Molari) services contract  advisory •  tracker specialist • .T-Mech (Mechanical) • General removal/assembly of components • M.Goyette hired on contract • T.Hessels(UCN Designer & .T-Mech)  ~ 50% (?) • Require 1 more .T-Mech(TRIUMF)  50% • Crane Crew • At start of shutdown (Jan.2 – 17)  remove/excavate shielding blocks • Intermittent (Jan.21 – Mar.26)  removal/placing of components • Near end of shutdown (Mar.27 – Apr.10)  restoring shielding+plug • Others • Contractors: Plumbing (Lockerbie), Electrical (Entech), Coring (West Coast) • Safety/RPG, Engineering (Civil, Electrical), Plant Group  Intermittent • Diagnostics & Controls  1AM5 (best efforts)

  4. UCN 2014 Installation: Alignment Plan 4 • Alignment Plan & Logistics • Plan being developed in consultation w/ Alignment group & D.Pearce • Purchase Order for laser-tracker rental from Hexagon Metrology • Alignment Plan Overview • Fiducialize magnets, frames & other B/L components w/ Laser Tracker • - Shoot array of points (upstream/downstream) on each component • Shoot Vault & 1A monuments w/ Laser Tracker & establish coord. system • Lay down grid of new monuments (Vault & 1A tunnel) & record • - Number/Locations of new monuments (consult Bruno/Mike) • Paint floor and/or lay down scribe lines • Mark drill location (and angle) on Immovable-block for coring • Install/Locate frames (Theodolite or Laser Tracker) • Install/Align magnets/components according to schedule • - Use Laser Tracker to position fiducializedpoints

  5. Meson Hall Clean-up 5 • M11 Cleanup Completed • Staging area for new Shielding • M13 Cleanup Completed • Staging area for “removed” blocks • Some blocks already moved to M13 • Jason’s layout for temp. block storage • “Boot-box” area for 1A access  M13 • Cleanup above BL1A/1B • Almost completed (thanks to Ron K.) • 46 items removed; ~11 items left to move (this week & after beam OFF) • Catalogue of items removed: •  https://ucn.triumf.ca/triumf/beamline/Catalog-MH-cleanup.pdf • Extra Blocks (6’ and smaller)  stage to M13 “monolith”

  6. Cleanup above BL1A/1B Floor Plan (SW Meson Hall) E Zone C (slides 29-59) Zone B (slides 15-28) Zone A (slides 5-14) N Gateway S W (From Dec/2012) Total number of items: 9 (zone A) + 13 (zone B) + 30 (zone C) = 52

  7. Floor Plan (SW Meson Hall) E Zone C (slides 29-59) Zone B (slides 15-28) Zone A (slides 5-14) N Gateway S W (From Dec/2012) Total number of items: 9 (zone A) + 13 (zone B) + 30 (zone C) = 52

  8. Floor Plan (SW Meson Hall) E Zone C (slides 29-59) Zone B (slides 15-28) Zone A (slides 5-14) N Gateway S W (Dec/2013) Objects rem. Total number of items: 1 (zone A) + 5 (zone B) + 3 (zone C) = 9(43 objects cleared)

  9. Floor Plan (SW Meson Hall) E Zone C (slides 29-59) Zone B (slides 15-28) Zone A (slides 5-14) N Gateway S W (Dec/2013) Objects added N2 N3 N1 N4 N5 Total number of items: 1 (zone A) + 5 (zone B) + 3 (zone C) = 9+ 5 “New items”

  10. Floor Plan (SW Meson Hall) E Zone C (slides 29-59) Zone B (slides 15-28) Zone A (slides 5-14) N Gateway S W (Dec/2013) Objects added (& removed) N2 N3 N1 N4 N5 Total number of items: 1 (zone A) + 5 (zone B) + 3 (zone C) = 9+ 2 “New items”

  11. Remaining items to move

  12. Remaining items to move this week Detector Group UCN R/H To M11: To Storage “Barn”: To top of M9, M11, M20 blocks: Beamlines R/H Beamlines

  13. Remaining items to move after beam OFF To Vault Roof: PIENU Beamlines T2K/Snolab Outside M11: EWB/Beamlines

  14. FINIS

  15. .T-Mech