An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CITY OF ST. PAUL PARK 2014 STREET & UTILITY IMPROVEMENT PROJECT CITY COUNCIL MEETING November 18, 2013

  2. Street Reconstruction Program

  3. Study Area • Pullman Avenue • 2nd Street to 6th Street: • 3rd Street • Pullman Avenue to 13th Avenue

  4. Existing Conditions Pullman Avenue (2nd Street to 3rd Street) Pullman Avenue (4th Street to 3rd Street)

  5. Proposed Street Improvements: Pullman Avenue • Complete Street Reconstruction • 2nd Street to 3rd Street: 36’ wide • 3rd Street to 6th Street: 44’ wide • Concrete Curb and Gutter • 2nd Street to 3rd Street: install new • 3rd Street to 6th Street: remove and replace • Concrete Sidewalk • 3rd Street to 6th Streeton north side

  6. Proposed Utility Improvements • Sanitary Sewer Improvements • Pullman Avenue between 2nd Street and 6th Street • Upgrade existing facilities to accommodate trunk sanitary sewer • Water Main Improvements • Pullman Avenue between 3rd Street and 6th Street • Maintenance records indicate numerous breaks • Frequency of breaks typically increases in cast iron pipe (CIP) water main more than 40 years in age • Storm Sewer Improvements • Pullman Avenue • Replace as necessary to install sanitary sewer and water main • 3rd Street • Standing water/icing in street • Accelerated pavement deterioration • Road patching as necessary to install storm sewer

  7. Project Costs • Total Estimated Project Cost: $1,460,690 • Pullman Avenue • Street and Storm Sewer$863,690 • Sanitary Sewer and Water Main $475,100 • 3rd Street • Storm Sewer $121,900

  8. Project Funding • Total Estimated Project Cost: $1,460,690 • Street and Storm Sewer Assessments $195,540 • Utility Assessments $13,000 • City Utility Funds $618,200 • City CIP Funds $633,950

  9. Estimated Assessments • Residential (33%) • Per front foot • $94.65 • Assessments • Range: $1,100 - $9,500 • Average: $4,500 • Commercial (40%) • Per front foot • $131.67 • Assessments • Range: $3,300 - $13,200 • Average: $6,300

  10. Similar Projects

  11. Preliminary Project Schedule • Neighborhood Open House Nov. 7, 2013 • Present Feasibility Report to City Council Nov. 18, 2013 • Project Public Hearing/Order Project Dec. 16, 2013 • Approve Plans/Authorize Bids Feb. 2014 • Assessment Hearing May 2014 • Construction June–Sept. 2014 • First Payment with Property Taxes May 2015

  12. 2016 Proposed Improvements • Complete Street Reconstruction • 36’ face-to-face of curb • Concrete Curb and Gutter • Install new

  13. 2016 Proposed Utility Improvements • Sanitary Sewer Improvements • 2nd Street between 11th Avenue and Pullman Avenue • Upgrade existing facilities to accommodate future trunk sanitary sewer for River’s Edge development to the south • Storm Sewer Improvements • Address flat slopes to ensure proper drainage • 11th Avenue between 2nd Street and 3rd Street • 2nd Street • 1st Street – between 10th Avenue and 11th Avenue • Sitlow Park drains to rock garden installed by Public Works • Storm water remains in rock garden until it has infiltrated • Rock garden has been know to hold water for several days • Road patching as necessary to install storm sewer

  14. Next Steps: • Resolution to Accept Feasibility Report and Set Public Hearing Date and Time • Proposed Public Hearing December 16, 2013

  15. Questions???