ATEC BRAC Update

ATEC BRAC Update. 154 Days Remain To BRAC End-Date 15 Sep 109 Days Remain To ATEC Ready Date 1 Aug. Cleon Raynor 14 April 11.

baxter
Download Presentation

ATEC BRAC Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ATEC BRAC Update 154Days Remain To BRAC End-Date 15 Sep 109Days Remain To ATEC Ready Date 1 Aug Cleon Raynor 14 April 11 (T)Provide our employees with BRAC execution & planning update (P) To keep all informed of ongoing actions so that we remain synchronized with minimal impact to mission.

  2. HQ ATEC & AEC BRAC Results

  3. HQ ATEC & AEC Report DateBreakout

  4. New HQs Build Update Current Construction Status • Glass Atrium Installed • Interior Atrium Stairs & Crosswalk Installed • 1st & 2nd Floor Dry-Wall Complete • Staircase Installed • All Dry Wall / Paint Complete • Freight Elevator Complete • Flooring Installation As of 7 Mar 11 Working • Change in Beneficial Occupancy Date • ACSIM Tracking – 19 Day Slip • Furniture Contract Awarded-install 4 May-29 June • Case – Goods on schedule • ACSIM Tracking – Ready Date Implications • IT-Security Synchronization • Contracts (e.g. IT Vendor, ADT) As of 7 Mar 11 ATEC Ready Date: 1 Aug 11

  5. Summary • ATEC HQs Bldg 87% complete, TRD is 1 August 11 • As of 4 April majority of ATEC - Alexandria Workforce at APG • Two-Phase Move : Phase 1: Oct 10 through 4 April 11(Move to APG) Phase 2: 5 April through 15 Sep 11 (Move to Hqs Bldg) • Weekly Planning/Coordination/Execution Meetings • NCR OPS Cell - close out IMP/PCIV; APG Team - APG