ATEC BRAC Update. 154 Days Remain To BRAC End-Date 15 Sep 109 Days Remain To ATEC Ready Date 1 Aug. Cleon Raynor 14 April 11.
E N D
ATEC BRAC Update 154Days Remain To BRAC End-Date 15 Sep 109Days Remain To ATEC Ready Date 1 Aug Cleon Raynor 14 April 11 (T)Provide our employees with BRAC execution & planning update (P) To keep all informed of ongoing actions so that we remain synchronized with minimal impact to mission.
New HQs Build Update Current Construction Status • Glass Atrium Installed • Interior Atrium Stairs & Crosswalk Installed • 1st & 2nd Floor Dry-Wall Complete • Staircase Installed • All Dry Wall / Paint Complete • Freight Elevator Complete • Flooring Installation As of 7 Mar 11 Working • Change in Beneficial Occupancy Date • ACSIM Tracking – 19 Day Slip • Furniture Contract Awarded-install 4 May-29 June • Case – Goods on schedule • ACSIM Tracking – Ready Date Implications • IT-Security Synchronization • Contracts (e.g. IT Vendor, ADT) As of 7 Mar 11 ATEC Ready Date: 1 Aug 11
Summary • ATEC HQs Bldg 87% complete, TRD is 1 August 11 • As of 4 April majority of ATEC - Alexandria Workforce at APG • Two-Phase Move : Phase 1: Oct 10 through 4 April 11(Move to APG) Phase 2: 5 April through 15 Sep 11 (Move to Hqs Bldg) • Weekly Planning/Coordination/Execution Meetings • NCR OPS Cell - close out IMP/PCIV; APG Team - APG