Army Team C4ISR BRAC Update. Presented By: Sue Nevin, G3/5 CECOM Life Cycle Management Command 8 October 2009. 1,131 “Boots on the Ground”. What We’ve Done. Phased Relocation Status and Timeline (FY07 – FY11). Groundbreaking For Permanent Facilities.
E N D
Army Team C4ISR BRAC Update Presented By: Sue Nevin, G3/5 CECOM Life Cycle Management Command 8 October 2009
1,131 “Boots on the Ground” What We’ve Done Phased Relocation Status and Timeline(FY07 – FY11) Groundbreaking For Permanent Facilities Time Now Phase 2 Early Relocation 340 positions (140 Vol.) Phase 1 Early Relocation 32 positions (11 Vol.) Phase 3 Early Relocation 1317 positions (542 Vol. Currently) Main Moves Into Permanent Facilities 2010 2007 2008 2009 2012 2011 In accordance with Report to Congress and BRAC Strategic Plan: Developed Phased Early Relocation strategy using temporary facilities at APG – combination of military, civilian volunteers, new hires and contractors Page 2 of 29
MTF GMS TOWER C2/CNT WEST GMS LAB HQ BES WEST HQ BES EAST Auditorium Page 3 of 29
GMS Lab & GMS Tower Estimated Date that Moves will begin: 1 August 2010 Building Occupancy: 1,410
HQ East & HQ West Estimated Date that Moves will begin: 1 October 2010 Building Occupancy: 2,143
C2/CNT West & Mission Training Facility Estimated Date that Moves will begin: 1 November 2010 Building Occupancy: 1,800
Army Team C4ISR Phase II Building Occupancy: 2,213 Consolidated North Power & Cooling C3/CNT East JSEC