1 / 22

Creating Effort Driven Schedules

Learn to create effort-driven project schedules efficiently in MS Project by understanding task types, resource allocation, and task dependencies. Follow step-by-step instructions and examples to optimize your project management process.

bcarrie
Download Presentation

Creating Effort Driven Schedules

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Creating Effort Driven Schedules

  2. Creating Effort Driven Schedules • Objectives • Understanding Your Job and the Tools Job • Understanding Task Types • Six Steps to an Effort Driven Project Schedule

  3. Understand Your Job, The Tools Job • Project Leader’s Job • Determine the amount of work (effort) the task will take(according to a documented procedure, remember?) • Determine which resource to assign to the task • Determine resource availability and calendar adjustments • Determine Task Dependencies • Manage Resource Over-allocations • MS Project’s Job • Calculate Duration of the Task • Calculate Start and Finish Dates • Help Identify Resource Over-allocations

  4. Understand Task Types • Fixed Unit Tasks • MS Project default, when effort driven scheduling is enabled • Adding more resources makes task duration shorter • Removing resources makes task duration longer • Fixed Work Tasks • All tasks of this type are effort driven • Tasks behave similarly to fixed unit tasks with regard to adding and deleting resources • Provides more flexibility than fixed unit tasks (IMHO) • Fixed Duration Tasks • Not recommended for effort driven tasks • Duration is kept constant when resources are added or removed • Work is added or removed when resources are added

  5. Example 1 • Purpose • Illustrate task types • Illustrate “The Rule” • Show how “The Rule” can affect tracking

  6. Example 1- Lessons Learned • Lessons Learned • Task Types are used to fix one of the variables in the equation: • Entering actual start and finish dates is equivalent to adjusting the task duration • Updating Task Actuals using the task form can give unreliable results*

  7. Effort Driven Schedules Your Job Tools Job • Six easy steps(42 substeps,19 caveats :) • Setup Tool Options and Project working times • Define Resources and their Working Times • Input the Work Breakdown Structure • Define Task Dependencies and Priorities • Assign Resources & Input Assignment Effort Estimates • Let MS Project Calculate Dates and Durations

  8. Step 1 - Set the Tool Options Set Default Task Type to Fixed Work Tools  Options  Schedule Tab Set Project Start Date Project  Project Information Project Information Dialog Tool Options Dialog

  9. Set Project Working Time Set Project Working Time Tools  Change Working Time Change Working Time Dialog • Edit the project calendar to allow for non-productive time • Use Non-working time to identify company holidays • Use Non-default working time to allow for project overhead

  10. Set Project Working Time (cont.) Set Duration Translations Tools  Options  Calendar Tab Tool Options Dialog • When you adjust the project calendar, adjust the calendar options accordingly

  11. Example 2 – Allowing for Overhead • Purpose • Illustrate what happens when calendar option do not align with the project calendar

  12. Example 2 – Lessons Learned • Account for non-productive time by: • adjusting the working times on the project’s standard calendar • and setting the calendar options accordingly • Recommend setting productive time to one of the following: • 50% - 4 hours per day, 20 hrs per week • 63% - 5 hours per day, 25 hours per week • 75% - 6 hours per day, 30 hours per week

  13. Step 2 – Define Your Resources Define Resources View  Resource Sheet Resource Sheet View in MS Project • Enter Resource Names and Max Units on Resource Sheet

  14. Max Units • Dedicated = 100% • Shared = some % • varying availability • Used by MS Project to identify resource over-allocations • Use Max Units to reflect the percentage of time a resource is assigned to your project • Max units field is not to be confused with the units field that is used for resource assignments

  15. Resource Availability • Use non working time for those out for full days • Use non default time those who work short days • Adjust resource calendars • to account for those people who do not work a standard week, or are unavailable • affect how assignments are scheduled

  16. Example 3 - Lessons Learned • Purpose • Illustrate the use of Max units field • Illustrate how the units field relates to Max units field • Illustrate how to use resources calendars

  17. Example 3 - Lessons Learned • The Max Units field: • should be used to designate what percentage of time a resource is assigned to your project • is used by MS Project to identify resource over allocations • Is not to be confused with the units field used for resource assignments • Individual Resource calendars are used to: • Adjust calendars for non-working times (i.e. vacations) and non-standard working times (part time resources) • They are not meant to be used to help you track project actuals

  18. Step 3 – Input the WBS Use Task Entry View View  More Views  Task Entry Task Entry View in MS Project Set Details to Resource Work Format  Details  Resource Work

  19. Step 4 - Task Dependencies & Priorities • Task Dependencies • Describes how a task is related to the start or finish of another task • Recommend using finish to start dependencies primarily • All tasks should have predecessors (apart from the first task) • Do not set dependencies between summary tasks • Can be used for resolving resource over-allocations (but not recommended)

  20. Step 5 – Assign Resources Task Entry View in MS Project Use task form to assign resources, workload, and adjustments

  21. Step 6 – Calculate Date and Durations • Allow MS Project to calculate task durations, start and finish dates • Remember your job and the tools job! • MS Project calculates durations using the formula: • Never enter in planned start dates. Doing so will create unwanted task constraints

  22. Effort Driven Scheduling • Not very well documented in literature, but . . . • Not rocket science • Understand • “The Rule” • Your Job and the Tools Job • Remember • Six step process for creating an effort driven schedule

More Related