280 likes | 453 Views
In Line Inspection Lessons Learned Eloy J. Blanco Al Verbrugge Senior Engineer Senior Engineer. Introduction. MidAmerican Energy Company (MEC) is primarily a LDC Operating in Iowa, Illinois, South Dakota, and Nebraska 797 miles of transmission lines. MidAmerican Energy Pipeline System.
E N D
In Line Inspection Lessons Learned Eloy J. Blanco Al Verbrugge Senior Engineer Senior Engineer
Introduction • MidAmerican Energy Company (MEC) is primarily a LDC • Operating in Iowa, Illinois, South Dakota, and Nebraska • 797 miles of transmission lines
Threat Assessment • EC & IC are threat to all of MEC’s pipelines • SCC is not a threat to any of our pipelines at this point • For MEC, ILI tools is the preferred method to assess a pipeline for Time-Dependent Threats (External Corrosion, Internal Corrosion, Stress Corrosion Cracking). MEC believes that Pressure Testing is not an applicable assessment method for Time Dependent Threats.
Criteria for In Line Inspection (ILI) • Number of segments and footage of HCA’s • Growth in the area • Existing condition of the pipeline • Cost
Criteria for ILI • Existing Condition If pipeline was built to handle ILI tools, the line will be pigged regardless of the footage of HCA’s or growth in the area.
Criteria for ILI • The next item to be considered was the total number of HCA segments and their footage. • If the line is not piggable, it would have to have a significant footage of HCA’s to be considered for pigging.
Criteria for ILI • Next, the growth along the pipeline was considered.
Criteria for ILI • Finally, the costs associated with modifying the line to handle ILI tools was incorporated into the decision making process.
Lines to be pigged • DSMS632-16” Line built in 2003. MAOP 800 psig. Can accommodate tools, no launcher/receiver • IAQC619-16” built in 1996. MAOP 960 psig. Verify if tee installed after original installation is barred; modify piping at terminus to handle L/R • ICCR691-16” Line built in 1991. MAOP 720 psig. No launcher/receiver; replace L/R 90o elbows installed during relocation; modify piping at terminus to handle L/R skids
Lines to be pigged • ICCR664-12 & 16” line built in 1959 & 1964. MAOP 600 psig. Significant amount of work required. Due to the amount of work, the line will be pigged in four stages. • ICCR653-10” line build in 1953. MAOP 600 psig. Significant amount of work required. Due to the amount of work require, the line will be pigged in three stages.
Line Modifications • None of our lines had launchers/receivers • Looked at three alternatives: • Rent launcher/receivers • Build permanent launcher/receivers • Build a temporary launcher/receiver skids that could handle 10”/12”/16”
Line Modifications • Since ICCR653 & ICCR664 run parallel to each other, parallel segments were taken out of service for modifications sequentially. This was done to minimize inconvenience to property owners. • Nevertheless, numerous pipeline shutdowns were required to perform the required modifications.
Line Modifications • Cost of gas is a significant item. Modifications to Lines ICCR653 and ICCR664 in 2007, required approximately $70,000 of gas to be vented to the atmosphere.
Line Modifications • Replaced non-standard port valves • Replaced standard elbows with hot bends. Original decision was to replace only bends tighter than 45o. Big Mistake! • Replaced box sags • Non-barred tees-tees were dug up and x-rayed • No field bends-fittings used instead
ROW Clearing • Had to do approximately 4 acres of clearing at a cost of $77,000.
Environmental & Permitting Concerns • Need to allow time for environmental and permitting
Existing Drawings • The availability and status of drawings is a problem with older lines • One set of drawings indicated that tees were barred , another indicated that they were not barred • Indicated bends, however the angle of the bends was not always indicated. Had to dig them out to determine. • Transition for wall thickness changes not indicated
ROW Availability • ROW availability is a problem • $100k at three sites • One location is still being negotiated • Temporary access may be an option
Running the Tool • ILI vendor availability-Although ILI vendors are extremely busy, MEC has not had any problems with scheduling the runs. • Run the tool on line or off line? • Speed control for ILI tools is essential (typically 3-5 mph) • If you use air, make sure it is dry air!
Running the Tool • Contact large customers early in the planning process • Develop contingency plan
Running the Tools • All vendors will tell you that their tool can make it thru standard radius elbows.
Running the Tool • Found a crushed elbow. Had to be cut out to remove the tool (cleaning tool with a tracker).
Running the Tool • Tracking the tool-use as many AGM’s as you can
Cleaning • Develop a line cleaning program. • MEC had to run over 30 cleaning pigs in one section of line.
Results • Results of a tool run on DSMS626 showed that that the line, as expected, was in excellent condition • Results on a section of ICCR664 showed, surprisingly, that the line is in excellent condition also. • No corrosion wall loss greater than 10% was found. • Manufacturing defects ~20% wall loss were found
Summary • Replace all l/r elbows • In your estimate, do not forget: • Gas vented • ROW clearing • ROW acquisition • Allow time for: • Permits • Environmental concerns • ROW acquisitions • If you use air to propel the tools; make sure it is dry • Use plenty of AGM’s • When you do your assessment, use features or AGM’s to locate anomalies