1 / 41

Overview

Overview. 9:30-9:45 Introduction and research overview 9:45-10:30 Energy benchmarking findings Savings-by-design cleanroom efficiency baselines 10:30-10:45 Break 10:45-11:30 Group discussion of successful efficiency projects and barriers 11:30-12:00 Top ten air system opportunities

benjamin
Download Presentation

Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Overview 9:30-9:45 Introduction and research overview 9:45-10:30 Energy benchmarking findings Savings-by-design cleanroom efficiency baselines 10:30-10:45 Break 10:45-11:30 Group discussion of successful efficiency projects and barriers 11:30-12:00 Top ten air system opportunities 12:00-1:00 Lunch 1:00-1:30 Demand controlled filtration and Standardized testing and reporting of fan-filter unit performance 1:30-2:15 Low hanging fruit – opportunities in cleanrooms 2:15-2:30 Q&A, Wrap-up, Discussion What is the audience background? What industries/institutions are represented?

  2. Energy intensive high-tech buildings 3

  3. Wide breadth of activities

  4. Prior cleanroom research • Roadmap for California Energy Commission • Cleanroom Programming Guide • Benchmarking 14 cleanrooms • Case study reports • California market assessment • Laboratory Design Guide

  5. Current cleanroom activities • Benchmarking and Best Practices • Fan-filter unit test procedure • Demand-controlled filtration • Minienvironment efficiency Cleanroom Measured Electricity End-use

  6. Energy Benchmarking • Improves business performance - saving energy puts $$ directly to the bottom line • Optimizing facility systems may improve: • Safety • Reliability • Production (yields) or Research results • Maintenance and operation • Energy performance • And may Lower capital cost • Some improvements are low or no cost

  7. Benchmarking benefits • Establish baseline to track performance over time • Enable comparisons to others • Prioritize where to apply resources • Best practices become apparent • Efficiency techniques can be applied to future projects

  8. Benchmarking- additional benefits • Reliability Improvement • Controls • Setpoints • Maintenance • Leaks • Motors, pumps, Fans • Filters • Chillers, boilers, etc. • Safety • Hazardous air flow

  9. What are the stakes? Utility bills from one case study: Billing daysConsumptionDollars Elec 368 38,084,148 kWh $2,549,330 Gas371 70,203 therms $43,715 approx 20,000 sq ft cleanroom in 68,000 sq ft building w/ $.065 ave. per kW

  10. LBNL energy benchmarking • Energy end-use was determined along with energy efficiency of key systems. • Energy efficiency recommendations were provided to each facility. These are being used to identify “best practices” • Prior benchmarking results available at: http://ateam.lbl.gov/cleanroom/benchmarking/ results.html

  11. Energy end-use

  12. Energy intensive systems We examine energy intensive systems Representative end-use

  13. System efficiency vs. production efficiency • Metrics allow comparison of air system efficiency regardless of process – e.g. cfm/kW or kW/cfm • Production metrics can mask inefficient systems – e.g. kW/cm2 (of silicon) or kW/lb of product

  14. Cleanroom air system metrics • Air systems – cfm/kW • Recirculation • Make-up • Exhaust • Cleanroom air-changes – ACH/hr • Recirculated, filtered air • Outside air (make-up and exhaust) • Average room air velocity- • ft/sec

  15. Recirculation systems Average 3440 Average 1953 LBNL Data Sematech Data 16

  16. Recirculation system hypothetical operating cost comparison

  17. Make-up air systems Average972 Average 946 LBNL Data Sematech Data 18

  18. Factors affecting make-up system efficiency • Resistance of make-up air path • Air handler/coil face velocity • Coil Pressure Drop • Duct/plenum sizing and layout • Adjacency of air handler(s) to cleanroom • Filters • Fans • Fan and motor efficiency • Variable Speed Fans • Pressurization, losses, and exhaust

  19. Air-change rates and air velocity Not an exact science… • The Institute of Environmental Sciences and Technology (IEST), and others, provide recommended recirculation air-change rates • Many large companies set their own criteria • Studies have shown that more airflow is not necessarily better • Philosophy of ceiling filter coverage varies • Pressurization/losses can have a large impact • Air changes and cleanroom protocol are both important

  20. Recirculation air-change rates and average velocities

  21. Ceiling filter coverage – achieving the same cleanliness level

  22. Chilled water systems efficiencies

  23. Standby generation loss • Several load sources • Heaters • Battery chargers • Transfer switches • Fuel management systems • Heaters alone (many operating hours) use more electricity than ever produced by the generator (few operating hours) Opportunity may be to reduce or eliminate heating, batteries, and chargers 24

  24. Component efficiencies also vary Fan-Filter Units 2800 cfm/kW Source: Industrial Technology Research Institute, Taiwan

  25. Measured UPS efficiency

  26. Case study Good news/Bad news Recirculation setback at night and on weekends was successfully utilized and dramatically saved energy Unfortunately air-change rates were higher than they needed to be and the system had a high pressure drop (resistance to airflow)

  27. Ducting to HEPA filters creates large pressure drop

  28. Case study – recirculation setback • Setback based solely on time clock, 8:00 PM-6:00 AM • No reported process problems or concerns from process engineers • 60% – 70% power reduction on turndown

  29. Recirculation setback – energy savings • Annual fan savings from daily and weekend setback: 1,250,000 kWhapproximately $138,000 • Cooling load reduction when setback: 234 kW65 tons

  30. Case study - recommendation Air-change rates exceeded IEST recommendations during daylight operation and were well above recommended minimums during setback. Further large reductions in energy use are possible by reducing air change rates and should not affect the process within the room.

  31. ISO 14644-4 (international standard for design and construction of cleanrooms) (Its OK to save energy!)

  32. What are we learning from cleanroom benchmarking? • Systems are often oversized • Contamination control can be achieved with reduced air change rates • Cleanliness ratings are often higher than needed • Rule of thumb criteria should be examined (e.g.: 90ft/min, air changes, filter coverage etc.) • Overcooling and subsequent reheat can be excessive • Chilled water pumping is often an opportunity • Chilled water temperature often is lower than needed

  33. Using benchmarks to set goals Building owners and designers can use benchmark data to set energy efficiency goals. • Cfm/KW • KW/ton • System resistance – i.e. pressure drop • Air handler face velocities • Others

  34. Recirculation system performance System Performance Target

  35. Statewide Savings-By-Design baselines Cleanroom baseline criteria Recirculation system • Metric: Watts/cfm • Determine watts by measurement or from design BHP W = BHPx746 0.91 • Determine flow from balance report or design documents • Baseline value is 0.43 W/cfm (2,325 cfm/kW) • Annual savings=(Baseline - Efficiency metric) x Annual cfm

  36. Savings-By-Design baselines Cleanroom baseline criteria Make-up air system • Metric: Watts/cfm • Determine watts by measurement or from design BHP W = BHPx746 0.91 • Determine flow from balance report or design documents • Baseline value is 1.04 W/cfm (961 cfm/kW) • Annual savings=(Baseline - Efficiency metric) x Annual cfm where annual cfm = .7 x design cfm

  37. Savings-By-Design baselines Additional cleanroom baseline criteria • Chilled water system • Hot water production • Compressed air

  38. Savings-By-Design Five largest energy savings opportunities: • Low face velocity in air handlers • Variable speed chillers • Free cooling for process loads • Dual temperature cooling loops • Recirculation air setback

  39. Best practices/conclusions • Clean space should be minimized • Better load determination is needed - actual load (not nameplate) and efficient strategies for load growth • Cleanliness classification needs to match contamination control problem (cleaner is not necessarily better) • Air-change rates can be optimized and save energy • Low pressure drop systems (low flow resistance) are much more efficient • Optimizing exhaust is an opportunity • There is no silver bullet – many strategies combined will provide best performance The answer is yes – cleanrooms can be more energy efficient!

  40. Questions? Thank you! http://hightech.lbl.gov

More Related