Workshop on Technology Development for reaching 250 MT (19-20)

This workshop aims to address the demand and gap for coal production, additional equipment required, and issues faced with suppliers. Suggestions for supply and maintenance of equipment will also be discussed.

benjaminw
Download Presentation

Workshop on Technology Development for reaching 250 MT (19-20)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Workshop on Technology Development for reaching250 MT (19-20) Mahanadi Coalfields Limited

  2. Estimated demand & Gap Demand of coal IN MT (at 100% satisfaction level) as per FSA/LOA

  3. Coal production projection Year wise upto 2019-20

  4. Additional Shovel required to achieve 250 Mty by 2019-20

  5. Additional Dumper required to achieve 250 Mty by 2019-20

  6. Additional Dozer required to achieve 250 Mty by 19-20

  7. Additional Drill required to achieve 250 Mty by 2019-20

  8. Additional Surface Miner required to achieve 250 Mty by 2019-20

  9. Additional Loading machine (Pay loader) required to achieve 250 Mty by 2019-20

  10. Additional equipment required for UG upto 2019-20

  11. Other P&M ( other than HEMM) requirement to achieve 250 MT

  12. Other P&M ( other than HEMM) requirement to achieve 250 MT

  13. Rapid Loading System including SILO requirement to achieve 250 MT

  14. Technological Development & Mechanization of Mines Proposed

  15. Award of Contracts

  16. Issues with BEML (A) Delay in supply of spare parts. Spare parts of a module is not supplied in full rather it is supplied in piecemeal due to which repair of particular assembly and equipment is delayed. (B) BE-1600 Hydraulic Excavator 9.5 cum. 06 nos. supplied to MCL are going under frequent breakdown, due to Failure of engines, Hydraulic pumps & Hydraulic tubes, Cooling system and other components since its commissioning.

  17. The performance of BEML :

  18. The performance of BEML :

  19. (C) The performance of BH-100 Ton Dumpers after warranty period is very poor due to failure of Engines, Transmission and other components. Performance is as below :

  20. (C) The performance of BH-100 Ton Dumpers after warranty period is very poor due to failure of Engines, Transmission and other components. Performance is as below :

  21. Recently, supplied BH-60 Ton Dumpers are giving problems like Cabin Vibration, Regular failure of suspension, Air Conditioning compressor mounting bolt loosening problem, Sensors are not working, Camera monitoring foundation bracket failure & Transmission pump failure etc. • (E) Recently supplied BD-355 Dozers are also not performing to the mark and giving troubles like : • Automatic release of blades sometimes • Misalignment of cabin • Non functioning of Air Conditioner • Fuel Injection Pumping problem • Starting problem etc.

  22. ISSUES WITH M/S.H.E.C., RANCHI There is general delay in supply of equipment as well as spare parts. As HEC is facing financial constraints, they are demanding advance payment for supply of equipment for recently ordered 10 cum. Electric Rope Shovel

  23. ISSUES WITH M/S. PROMTRACTOR (JSC), RUSSIA Performance of 15 nos. 410 HP Dozers are very very poor due to abnormal failure of engine & transmission even in warranty period. The performance is as below : M/s. Promtractor (JSC), Russia has no Indian service provider for supply of spare parts and maintenance and also not supporting well for supply of spare parts and services.

  24. Thank you

  25. SUGGESTIONS FOR SUPPLY AND MAINTENANCE OF EQUIPMENT • All HEMM should be supplied with Guaranteed Spare Parts Supply (GPS) or Maintenance and Repair Contract (MARC) for life time.

  26. SUGGESTIONS FOR SUPPLY AND MAINTENANCE OF EQUIPMENT • Guarantee for initial 2-3 years is meaningless as machine will perform initially better than when it gets older after 03 years. Hence, guarantee for later period is more important. • Cost of equipment quoted is very less but spare parts are very costly which ultimately result into higher cost of production. If life cycle cost is adopted this can be eliminated. • Buy back system is to be incorporated in case of spare parts which are not consumed during warranty period. Some manufacturers are reluctant for life time guarantee due to uncertainty in foreign currency fluctuation. This problem can be sorted out by incorporating currency escalation/de-escalation clause.

  27. Modification in Proveness criteria • 4-5 years satisfactory performance may be introduced instead of one year as per existing standard NIT. • At least 30-40% of the tendered quantity may be considered for meeting the prove ness criteria instead of at least one number as per existing standard NIT. • Tender finalization should be 60/40 basis as per earlier system to have a check on L-1 bidder both in price as well as performance. • The equipment which are not having base in India should not be given chance for participation in open tender as there is also problem of spare and service support because of non availability of India Agent. There should be a provision of consignment store having major population nearer to the project.